HRVATSKI SABOR
29
Na temelju članka 89. Ustava Republike Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU IZMEĐU REPUBLIKE HRVATSKE I RAZVOJNE BANKE VIJEĆA EUROPE ZA PROJEKT LD 2056 (2020) – PODRŠKA MJERAMA U REPUBLICI HRVATSKOJ, POVEZANIH S PANDEMIJOM BOLESTI COVID-19 – INSTRUMENT FINANCIRANJA JAVNOG SEKTORA
Proglašavam Zakon Zakon o potvrđivanju Okvirnog ugovora o zajmu između Republike Hrvatske i Razvojne banke Vijeća Europe za Projekt LD 2056 (2020) – Podrška mjerama u Republici Hrvatskoj, povezanih s pandemijom bolesti COVID-19 – instrument financiranja javnog sektora, koji je Hrvatski sabor donio na sjednici 18. svibnja 2020.
Klasa: 011-01/20-01/87
Urbroj: 71-10-01/1-20-2
Zagreb, 3. kolovoza 2020.
Predsjednik
Republike Hrvatske
Zoran Milanović, v. r.
ZAKON
O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU IZMEĐU REPUBLIKE HRVATSKE I RAZVOJNE BANKE VIJEĆA EUROPE ZA PROJEKT LD 2056 (2020) – PODRŠKA MJERAMA U REPUBLICI HRVATSKOJ, POVEZANIH S PANDEMIJOM BOLESTI COVID-19 – INSTRUMENT FINANCIRANJA JAVNOG SEKTORA
Članak 1.
Potvrđuje se Okvirni ugovor o zajmu između Republike Hrvatske i Razvojne banke Vijeća Europe za Projekt LD 2056 (2020) – Podrška mjerama u Republici Hrvatskoj, povezanih s pandemijom bolesti COVID-19 – instrument financiranja javnog sektora, potpisan u Parizu 7. srpnja 2020. i u Zagrebu 15. srpnja 2020. u izvorniku na engleskom jeziku.
Članak 2.
Tekst Ugovora iz članka 1. ovoga Zakona, u izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik, glasi:
LD 2056 (2020)
FRAMEWORK LOAN AGREEMENT
BETWEEN REPUBLIC OF CROATIA AND COUNCIL OF EUROPE DEVELOPMENT BANK
– Supporting measures in the Republic of Croatia, related to COVID-19 pandemic – Public Sector Financing Facility
THE REPUBLIC OF CROATIA (hereinafter, the «Borrower»), represented by the Ministry of Finance, on the one hand
and
COUNCIL OF EUROPE DEVELOPMENT BANK, international organisation with its headquarters at 55, Avenue Kléber, 75116 Paris, France (hereinafter, the «CEB» or the «Bank» and together with the Borrower, the «Parties» and each a «Party»), on the other hand,
WHEREAS
(A) Having regard to the loan application submitted by the Republic of Croatia on 27 April 2020, approved by the CEB’s Administrative Council written procedure on 12 May 2020,
(B) Having regard to the Third Protocol to the General Agreement on Privileges and Immunities of the Council of Europe dated 6 March 1959,
(C) Having regard to the CEB’s Loan Regulations, as adopted by the CEB’s Administrative Council Resolution 1587 (2016) (hereinafter, the «Loan Regulations»),
(D) Having regard to the CEB’s Loan and Project Financing Policy, as adopted by the CEB’s Administrative Council Resolution 1611 (2019) (hereinafter, the «Loan Policy»),
(E) Having regard to the CEB’s Environmental and Social Safeguards Policy, as adopted by the CEB’s Administrative Council Resolution 1588 (2016) (hereinafter, the «Environmental and Social Safeguards Policy»),
(F) Having regard to the CEB’s Procurement Guidelines, as adopted by the CEB’s Administrative Council in September 2011 (hereinafter, the «Procurement Guidelines»),
HEREBY AGREE AS FOLLOWS:
1. INTERPRETATION
1.1 Definitions
The following terms shall have the meaning indicated below, except as the context requires otherwise:
«Agreement» means this Framework loan agreement, including its appendices.
«Allocation» means the commitment of a Tranche by the Borrower to the eligible Sub-Project even if such Tranche has not yet been paid out under the Project.
«Allocation Period» has the meaning specified under Sub-clause 5.2.
«Business Day» means in relation to payments in Euro, any day on which TARGET 2 (the Trans European Automated Real-time Gross Settlement Express Transfer system) is operating.
«Closing Date» means the date specified under Appendix 1 hereto from which no further disbursements may be requested by the Borrower.
«Completion Report» has the meaning specified under Sub-clause 6.1(b).
«Components» means the eligible sectors of action defined under Appendix 1 hereto.
«Currency» means, for the purposes of the Agreement, Euro.
«Day Count Convention» means the convention for determining the number of days between two dates and the number of days in a year specified in the relevant Disbursement Notice.
«Debt Instrument» means (i) any loan or other form of financial indebtedness; (ii) an instrument, including any receipt or statement of account, evidencing or constituting an obligation to repay a loan, deposit, advance or similar extension of credit (including without limitation any extension of credit under a refinancing or rescheduling agreement), (iii) a bond, note, debt security, debenture or similar written evidence of financial indebtedness; or (iv) an instrument evidencing a guarantee of an obligation constituting financial indebtedness of another.
«Default Interest Rate» has the meaning specified under Sub-clause 4.9.
«Disbursement Date» means the date on which a Tranche is scheduled to be disbursed pursuant to the applicable Disbursement Notice.
«Disbursement Notice» has the meaning specified under Sub-clause 4.3(b).
«Disbursement Request» has the meaning specified under Sub-clause 4.3(a).
«Early Reimbursement Confirmation» has the meaning specified under Sub-clause 4.7.
«Early Reimbursement Costs» has the meaning specified under Sub-clause 4.7.
«Early Reimbursement Date» has the meaning specified under Sub-clause 4.7.
«Early Reimbursement Notice» has the meaning specified under Sub-clause 4.7.
«Effective Date» means the date of entry into force of the Agreement resulting from Clause 18.
«EU» means the European Union.
«EURIBOR» means the percentage rate per annum quoted on the page EURIBOR01 of the Thomson Reuters screen (or on a successor page which replaces the Thomson Reuters’ page EURIBOR01) at or about 11 a.m. Brussels time on the Interest Determination Date as the Euro interbank offered rate administrated by the European Money Market Institute (or any other entity which takes over the administration of that rate) for the same period as the relevant Interest Period.
If the relevant Interest Period is not the same as a period quoted by Thomson Reuters, the applicable EURIBOR shall be the percentage rate per annum resulting from a linear interpolation by reference to two (2) EURIBOR rates for Euro term deposits, one of which is applicable for a period of whole months next shorter and the other for a period of whole months next longer than the length of the relevant Interest Period.
«Euro» and the sign «EUR» means the lawful currency of the Member States of the EU which from time to time adopt it as their currency in accordance with the relevant provisions of the Treaty of the EU and the Treaty on the Functioning of the EU or their succeeding treaties.
«European Convention on Human Rights» means the Convention for the Protection of Human Rights and Fundamental Freedoms dated 4 November 1950, CETS No. 5, as amended from time to time.
«European Social Charter» means the European Social Charter dated 3 May 1996, CETS No. 163, as amended from time to time.
«Final Beneficiaries» are specified under Appendix 1 hereto as the group benefitting from the social effects of the Project.
«Fixed Interest Rate» means the interest rate per annum specified in the applicable Disbursement Notice.
«Floating Interest Rate» means the interest rate per annum determined by adding or subtracting the Spread specified in the applicable Disbursement Notice to or from, as the case may be, the Reference Rate.
For the avoidance of doubt, when the determination of the Floating Interest Rate results in a negative interest rate (due to a quoted negative Reference Rate, to the operation of a Spread that is subtracted from the Reference Rate or to any other circumstances), the interest to be paid by the Borrower for the Interest Period shall be deemed to be zero.
«Interest Determination Date» means, for the purposes of determination of a Floating Interest Rate, the day falling two (2) Business Days prior to the first day of the Interest Period, unless otherwise specified in the relevant Disbursement Notice.
«Interest Payment Dates» means the dates for the payment of interest corresponding to the relevant Interest Period specified in the applicable Disbursement Notice.
«Interest Period» means the period commencing on an Interest Payment Date and ending on the day immediately prior to the following Interest Payment Date, provided that the first Interest Period applicable to each Tranche shall commence on the Disbursement Date and end on the day immediately prior to the next Interest Payment Date.
«Loan» means the loan granted to the Borrower by the CEB by means of the Agreement.
«Loan Amount» means the amount specified under Sub-clause 4.1.
«Market Disruption Event» has the meaning specified under Sub-clause 4.10.
«Material Adverse Change» means any event which, in CEB’s opinion, (i) materially impairs the Borrower’s ability to perform its financial obligations under the Agreement; or (ii) adversely affects any Security provided by the Borrower or a third-party to secure the due performance of the Borrower’s financial obligations under the Agreement.
«Maturity Date» means the last Principal Repayment Date for each Tranche specified in the applicable Disbursement Notice.
«Modified Following Business Day Convention» means a convention whereby if a specified date would fall on a day which is not a Business Day, such date would be the first following day that is a Business Day unless that day falls in the next calendar month, in which case that date would be the first preceding day that is a Business Day.
«Principal Repayment Date(s)» means the date(s) for the repayment(s) of principal under each Tranche specified in the applicable Disbursement Notice.
«Principal Repayment Period» means with respect of each Tranche the period running from its Disbursement Date to its Maturity Date.
«Progress Report» has the meaning specified under Sub-clause 6.1(a).
«Prohibited Practices» has the meaning specified under Sub-clause 5.8.
«Project» means the programme of eligible Sub-projects set forth under Appendix 1 hereto to be partially financed with the Loan approved by the CEB’s Administrative Council with ref. LD 2056 (2020).
«Reference Rate» means EURIBOR for a Floating Interest Rate Tranche denominated in Euro.
«Security» means any agreement or arrangement creating a preferential rank, a preferential right of payment, a collateral or guarantee of any nature whatsoever which might confer enhanced rights upon third parties.
«Spread» means, in connection with a Floating Interest Rate Tranche, the fixed-spread to the Reference Rate (being either plus or minus) specified in basis points in the applicable Disbursement Notice.
«Sub-project» means an eligible investment scheme to be financed under the Project.
«Tranche» means an amount disbursed or to be disbursed under the Loan.
1.2 Construction
Unless the context otherwise requires, references to:
(a) this Agreement shall be construed as references to this Agreement as supplemented, amended or restated from time to time;
(b) «Clauses», «Sub-clauses» and «Recitals» shall be construed as references to clauses, sub‑clauses and recitals respectively of this Agreement; and
(c) words importing the singular shall include the plural and vice-versa.
1.3 Headings
Headings in this Agreement have no legal significance and do not affect its interpretation.
1.4 Rounding
For the purposes of any calculations referred to in this Agreement:
• all percentages resulting from such calculations other than those determined through the use of interpolation will be rounded, if necessary, to the nearest one hundred-thousandth of a percentage point (e.g., 9.876541% (or .09876541) being rounded down to 9.87654% (or .0987654) and 9.876545% (or .09876545) being rounded up to 9.87655% (or .0987655));
• all percentages determined through the use of linear interpolation by reference to two (2) relevant Reference Rates will be rounded, if necessary, in accordance with the method set forth in subsection (a) above, but to the same degree of accuracy as the two (2) rates used to make the determination (except that such percentages will not be rounded to a lower degree of accuracy than the nearest one thousandth of a percentage point (0.001%)); and
• all currency amounts used in or resulting from the above calculations will be rounded, unless otherwise specified in the relevant Currency definition, to the nearest two decimal places in the relevant currency (with .005 being rounded upwards (e.g., .674 being rounded down to .67 and .675 being rounded up to .68).
2. CONDITIONS
The Loan is granted under the general conditions of the Loan Regulations and under the special conditions of the Agreement.
3. PURPOSE
The CEB grants the Loan to the Borrower, who accepts it, solely for the purpose of financing the Project as described under Appendix 1 hereto.
Any change to the way the Loan is applied that has not received the CEB’s approval would constitute an event in the terms of Article 3.3 (h) of the Loan Regulations and may give rise to the early reimbursement, suspension or cancellation of the Loan under the terms of Articles 3.3 (Early reimbursement of disbursed loans), 3.5 (Suspension by the Bank of undisbursed loans) and 3.6 (Cancellation by the Bank of undisbursed loans) of the Loan Regulations.
4. FINANCIAL CONDITIONS
4.1 Loan Amount
The Loan Amount is:
Two hundred million Euros
EUR 200,000,000
4.2 Disbursement Amount
The Loan shall be disbursed in a minimum of two (2) Tranches.
The amount of each Tranche shall be determined according to the absorption capacity of the Project. The amount of the first Tranche shall not exceed seventy five per cent (75%) of the Loan Amount.
4.3 Disbursement Procedure
The disbursement of each Tranche is determined through the following procedure:
(a) Disbursement Request
Prior to each disbursement, the Borrower shall submit to the CEB a disbursement request substantially in the form set out under Appendix 3 hereto (hereinafter, a «Disbursement Request»).
A Disbursement Request shall specify the:
(i) Currency(ies) and amount(s) for the Tranche;
(ii) Disbursement Date; such Disbursement Date shall be a Business Day falling at least five (5) Business Days but not later than twenty (20) Business Days after the date of the Disbursement Request;
(iii) Principal Repayment Date(s), including the Maturity Date, taking into account that the Principal Repayment Period for each Tranche shall not exceed twelve (12) years, including a grace period not greater than three (3) years;
(iv) maximum Fixed Interest Rate or maximum Spread to the Reference Rate;
(v) Interest Period and Interest Payment Dates;
(vi) Day Count Convention and Business Days; and
(vii) Borrower’s account for payments.
Each Disbursement Request delivered to the CEB shall be irrevocable, unless otherwise agreed in writing by the CEB.
(b) Disbursement Notice
If the CEB receives a Disbursement Request that complies with the Disbursement Request requirements set out in Sub-clause 4.3(a) above, and if all other relevant Disbursement Conditions as defined in Sub-clause 4.5 (Disbursement Conditions) below have been fulfilled by the Borrower, the CEB shall deliver to the Borrower a disbursement notice substantially in the form set out under Appendix 3 hereto (hereinafter, a «Disbursement Notice»). Each Disbursement Notice shall be delivered at least two (2) Business Days before the proposed Disbursement Date.
A Disbursement Notice shall specify:
(i) Currency(ies) and amount(s) for the Tranche;
(ii) Disbursement Date;
(iii) Principal Repayment Period and Principal Repayment Date(s), including the Maturity Date;
(iv) Fixed Interest Rate or Spread to the Reference Rate;
(v) Interest Period and Interest Payment Dates;
(vi) Day Count Convention and Business Days; and
(vii) Borrower’s and CEB’s accounts for payments.
If the Borrower has submitted to the CEB a Disbursement Request in which the Borrower has not proposed a Fixed Interest Rate or a Floating Interest Rate, the Borrower shall be deemed to agree in advance to the one subsequently specified by the CEB in the Disbursement Notice.
A Disbursement Notice matching the elements included in a Disbursement Request shall constitute an irrevocable and unconditional commitment on the part of the Borrower to borrow from the CEB and on the part of the CEB to disburse to the Borrower the Tranche under the terms and conditions specified in the Disbursement Notice.
Notwithstanding the above, if the CEB has not delivered a Disbursement Notice within ten (10) Business Days following the receipt of a Disbursement Request, the relevant Disbursement Request shall be deemed as cancelled.
4.4 Disbursement Period
Unless otherwise agreed in writing by the CEB, the Borrower shall not be entitled to:
(i) the issue of a Disbursement Request for the first Tranche beyond twelve (12) months after the Effective Date;
(ii) the issue of any further Disbursement Request beyond eighteen (18) months after the last disbursement; or
(iii) the issue of any further Disbursement Request beyond the Closing Date specified under Appendix 1 hereto.
4.5 Disbursement Conditions
(a) Conditions precedent to the Disbursement Request for the first Tranche:
(i) Legal opinion in English issued by the Minister of Justice confirming to the CEB’s satisfaction, substantially in the form set out under Appendix 2 hereto, that the Agreement has been duly executed by authorised representatives of the Borrower and that the Agreement is valid, binding and enforceable in accordance with its terms in the Borrower’s jurisdiction.
(ii) Evidence in English (e.g., Statute, By-laws, Board Resolution, Power of Attorney, etc.) to the CEB’s satisfaction of the person(s) authorised to execute the Agreement and the Disbursement Requests on behalf of the Borrower, together with the authenticated specimen of the signature(s) of such person(s).
(b) Conditions precedent to any further Disbursement Request:
(i) In the event there has been a change regarding the person(s) authorised to execute Disbursement Requests on behalf of the Borrower, the Borrower shall provide CEB with updated evidence of the person(s) authorised to execute the corresponding Disbursement Requests on behalf of the Borrower, together with the authenticated specimen of the signature(s) of such person(s).
(ii) Progress Report confirming to the CEB’s satisfaction the full Allocation of the previous Tranche.
4.6 Repayment
On any Principal Repayment Date, the Borrower shall repay the principal of each Tranche due on that Principal Repayment Date in accordance with the terms set forth in the applicable Disbursement Notice.
4.7 Early Reimbursement
(a) Mechanics
If in any event specified in this Agreement referring to this Sub-clause the Borrower ought to reimburse prior to maturity all or part of a Tranche, the Borrower shall give at least a one (1) month prior written notice to the CEB (hereinafter, the «Early Reimbursement Notice») specifying the amounts to be reimbursed, the date on which the reimbursement will take place (hereinafter, the «Early Reimbursement Date») and, upon prior consultation with the CEB, the maximum Early Reimbursement Costs. The Early Reimbursement Date shall fall on an Interest Payment Date, unless otherwise agreed in writing by the CEB.
Upon receipt of the Early Reimbursement Notice, the CEB shall send a written notice to the Borrower (hereinafter, the «Early Reimbursement Confirmation»), not later than five (5) Business Days prior to the Early Reimbursement Date, indicating the accrued interest due thereon and the Early Reimbursement Costs in accordance with Sub-clause 4.7(b).
An Early Reimbursement Confirmation matching the elements included in an Early Reimbursement Notice shall constitute an irrevocable and unconditional commitment on the part of the Borrower to reimburse the relevant amounts to the CEB under the terms and conditions specified in the Early Reimbursement Confirmation.
If the Borrower partially reimburses a Tranche, the reimbursed amount shall be applied pro rata to each outstanding principal repayment. In such an event, the Early Reimbursement Confirmation shall accordingly include an adjusted repayment schedule which shall be binding on the Borrower.
(b) Early Reimbursement Costs
The Early Reimbursement Costs resulting from early reimbursement in accordance with Sub-clause 4.7(a) shall be determined by the CEB on the basis of the costs to it of redeploying the amount to be reimbursed from the Early Reimbursement Date to the Maturity Date, including any related costs, such as unwinding any underlying hedging arrangements. The costs of redeployment will be established on the basis of the difference between the original rate and the redeployment rate, which shall be determined by the CEB on the basis of market conditions on the date of the Early Reimbursement Notice.
4.8 Interest Determination
The Borrower shall pay interest on the principal of each Tranche from time to time outstanding during each Interest Period at the Fixed Interest Rate/Floating Interest Rate specified in the applicable Disbursement Notice.
Interest shall (i) accrue from and including the first day of the Interest Period to but excluding the last day of such Interest Period; and (ii) be due and payable on the Interest Payment Dates specified in the applicable Disbursement Notice. Interest shall be calculated on the basis of the Day Count Convention specified in the relevant Disbursement Notice.
In the case of Floating Interest Rate Tranches, the CEB shall determine on each Interest Determination Date the interest rate applicable during the relevant Interest Period in accordance with the Agreement and promptly give notice thereof to the Borrower. Each determination by the CEB shall be final, conclusive and binding upon the Borrower unless shown by the Borrower to the satisfaction of the CEB that any such determination has involved manifest error.
4.9 Default Interest Rate
In the event that the Borrower fails to pay, in full or in part, any amount under the Agreement, and notwithstanding any other recourse available to the CEB under the Agreement or otherwise, the Borrower shall pay interest on such unpaid amounts from the due date until the date of receipt of such payment by the CEB at the interest rate per annum equal to the one-month EURIBOR quoted on the due date plus two hundred and fifty basis points (250 bps) (hereinafter, the «Default Interest Rate»).
The applicable Default Interest Rate shall be updated every thirty (30) calendar days.
4.10 Market Disruption Event
The CEB shall promptly, upon becoming aware of it, notify to the Borrower that a Market Disruption Event has occurred.
For the purposes of the Agreement, «Market Disruption Event» refers to the following circumstances:
(a) The Reuters page referred to under the EURIBOR definition does not indicate the required details or is not accessible.
Under such a Market Disruption Event, the applicable EURIBOR shall be the percentage rate per annum determined by the CEB to be the arithmetic mean of the rates at which loans in Euro, in an amount identical or nearest comparable to the Loan amount in question and for a period identical or nearest comparable to the relative Interest Period, are offered on the Interest Determination Date by three (3) leading banks in the EU interbank market selected by the CEB. If at least two (2) quotations are provided, the applicable EURIBOR for that Interest Determination Date shall be the arithmetic mean of all quotations provided.
If only one (1) or no quotation is provided, the applicable EURIBOR shall be the percentage rate per annum determined by the CEB to be the arithmetic mean of the rates at which loans in Euro, in an amount identical or nearest comparable to the Loan amount in question and for a period identical or nearest comparable to the relative Interest Period, are offered on the second Business Day after the beginning of the relevant Interest Period by major banks in the EU interbank market selected by the CEB.
(b) The CEB determines that it is not possible to determine the applicable Reference Rate in accordance with paragraph (a) above.
Under such a Market Disruption Event, the applicable Floating Interest Rate shall be replaced by the rate that expresses as a percentage rate per annum the cost to the CEB of funding the Loan from whatever source the CEB may reasonably select.
(c) At any time between the delivery of a Disbursement Notice and the Disbursement Date the CEB reasonably determines that there are exceptional and unexpected circumstances of an economic, financial, political or other external nature adversely affecting the CEB’s access to its sources of funding.
Under such a Market Disruption Event, the CEB shall be entitled to cancel at no cost the scheduled disbursement.
In the case of the Market Disruption Events set forth under items (a) and (b) above:
(i) If the Borrower so requires, the Parties, acting in good faith, shall enter into negotiations for a period of not more than thirty (30) calendar days in order to agree on an alternative to the applicable EURIBOR. If no agreement is reached, the Borrower may proceed with early reimbursement on the next Interest Payment Date in the terms provided under Sub-clause 4.7.
(ii) The CEB shall have the right, acting in good faith and in consultation with the Borrower to the extent reasonably practicable, to change the duration of any subsequent Interest Period to thirty (30) calendar days or less by sending to the Borrower a notice thereof. Any such change to an Interest Period shall take effect on the date specified by the CEB in such notice.
If the CEB determines that the relevant Market Disruption Event no longer exists, then, subject to any further Market Disruption Event occurring or existing, the Floating Interest Rate and/or Interest Period applicable to any relevant Tranche shall revert, from the first day of the following Interest Period to being calculated in accordance with the Floating Interest Rate and Interest Period specified in the relevant Disbursement Notice.
4.11 Payments
All the amounts due by the Borrower under this Agreement are payable in the Currency of each Tranche to the CEB’s account indicated in the applicable Disbursement Notice. Any payment under this Agreement shall be made on a Business Day subject to the Modified Following Business Day Convention. Any payment shall be deemed paid when the CEB has received the amount on its account.
The Borrower or the bank instructed by the Borrower, as the case may be, shall send a written payment notice to the CEB at least five (5) Business Days before payment of any amounts due under this Agreement.
5. PROJECT IMPLEMENTATION
The Borrower shall implement the Project in accordance with the Agreement.
Failure to comply with the Project Implementation undertakings set forth hereby under Clause 5 would constitute, irrespective of any other applicable provision of the Loan Regulations, an event in the terms of Article 3.3 (h) of the Loan Regulations and may give rise to (i) the relevant Sub‑project being declared ineligible for Allocation under the Project; and/or (ii) the early reimbursement, suspension or cancellation of the Loan, in whole or in part, under the terms of Articles 3.3 (Early reimbursement of disbursed loans), 3.5 (Suspension by the Bank of undisbursed loans) and 3.6 (Cancellation by the Bank of undisbursed loans) of the Loan Regulations.
5.1 Duty of Care
The Borrower shall apply all care and diligence, and shall exercise all typically used means (including, but not limited to, legal, financial, managerial and technical) required for the proper implementation of the Project.
5.2 Allocation Period
The Borrower shall allocate each Tranche to the Project within twelve (12) months after the relevant Disbursement Date (the «Allocation Period»).
If a Tranche disbursed by the CEB is not allocated to the Project or is only partially allocated to it within the Allocation Period, the Borrower shall reimburse the unallocated amounts to the CEB in accordance with Sub-clause 4.7.
5.3 Project Costs
The Tranches disbursed under the Loan shall not exceed ninety per cent (90%) of the total incurred eligible costs of the Project. If the Tranches disbursed under the Loan exceed the above ninety per cent (90%) (by reduction of the total eligible costs or otherwise), the Borrower shall reimburse the surplus to the CEB in accordance with Sub-clause 4.7.
Should the total eligible costs of the Project increase or be revised for whatever reason, the Borrower shall ensure that the additional financial resources for the completion of the Project are available without recourse to the CEB. The plans to finance the increased costs shall be communicated to the CEB without delay.
5.4 Project Specific Undertakings
The Borrower shall ensure that:
(i) all the land, real property rights and permits required for the implementation of the Project are timely available; and
(ii) all assets and plants under the Project are permanently insured and maintained in accordance with international best practices.
5.5 Procurement
Procurement of supplies, works and services to be financed under the Project shall comply with the Procurement Guidelines.
5.6 Environmental and Social Safeguards
The Borrower shall implement the Project in conformity with the requirements set forth in the Environmental and Social Safeguards Policy. In particular, should the project require an Environmental Impact Assessment (EIA) in accordance with the Environmental and Social Safeguards Policy, the Borrower shall notify CEB and ensure that the appropriate Environmental and Social Impact assessment(s) are undertaken in accordance with the requirements of the Environmental and Social Safeguards Policy. The Borrower shall ensure that relevant environmental and social assessment documentation is made available for the CEB’s review when requested.