HRVATSKI SABOR
28
Na temelju članka 89. Ustava Republike Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU UGOVORA O ZAJMU IZMEĐU REPUBLIKE HRVATSKE I MEĐUNARODNE BANKE ZA OBNOVU I RAZVOJ ZA PROJEKT OBNOVE NAKON POTRESA I JAČANJA PRIPRAVNOSTI JAVNOG ZDRAVSTVA
Proglašavam Zakon o potvrđivanju Ugovora o zajmu između Republike Hrvatske i Međunarodne banke za obnovu i razvoj za Projekt obnove nakon potresa i jačanja pripravnosti javnog zdravstva, koji je Hrvatski sabor donio na sjednici 31. srpnja 2020.
Klasa: 011-01/20-01/86
Urbroj: 71-10-01/1-20-2
Zagreb, 3. kolovoza 2020.
Predsjednik
Republike Hrvatske
Zoran Milanović, v. r.
ZAKON
O POTVRĐIVANJU UGOVORA O ZAJMU IZMEĐU REPUBLIKE HRVATSKE I MEĐUNARODNE BANKE ZA OBNOVU I RAZVOJ ZA PROJEKT OBNOVE NAKON POTRESA I JAČANJA PRIPRAVNOSTI JAVNOG ZDRAVSTVA
Članak 1.
Potvrđuje se Ugovor o zajmu između Republike Hrvatske i Međunarodne banke za obnovu i razvoj za Projekt obnove nakon potresa i jačanja pripravnosti javnog zdravstva, potpisan u Zagrebu 1. i 2. srpnja 2020. u izvorniku na engleskom jeziku.
Članak 2.
Tekst Ugovora iz članka 1. ovoga Zakona, u izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik, glasi:
LOAN NUMBER 9127-HR
LOAN AGREEMENT
(EARTHQUAKE RECOVERY AND PUBLIC HEALTH PREPAREDNESS PROJECT) BETWEEN REPUBLIC OF CROATIA AND INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT
LOAN AGREEMENT
AGREEMENT dated as of the Signature Date between REPUBLIC OF CROATIA («Borrower») and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT («Bank»). The Borrower and the Bank hereby agree as follows:
Article I
GENERAL CONDITIONS; DEFINITIONS
1.01. The General Conditions (as defined in the Appendix to this Agreement) apply to and form part of this Agreement.
1.02. Unless the context requires otherwise, the capitalized terms used in this Agreement have the meanings ascribed to them in the General Conditions or in the Appendix to this Agreement.
Article II
LOAN
2.01. The Bank agrees to lend to the Borrower the amount of one hundred and eighty three million and nine hundred thousand Euro (€183,900,000), as such amount may be converted from time to time through a Currency Conversion («Loan»), to assist in financing the project described in Schedule 1 to this Agreement («Project»).
2.02. The Borrower may withdraw the proceeds of the Loan in accordance with Section III of Schedule 2 to this Agreement.
2.03. The Front-end Fee is one quarter of one percent (0.25%) of the Loan amount.
2.04. The Commitment Charge is one quarter of one percent (0.25%) per annum on the Unwithdrawn Loan Balance.
2.05. The interest rate is the Reference Rate plus the Fixed Spread or such rate as may apply following a Conversion; subject to Section 3.02(e) of the General Conditions.
2.06. The Payment Dates are May 15 and November 15 in each year.
2.07. The principal amount of the Loan shall be repaid in accordance with Schedule 3 to this Agreement.
Article III
PROJECT
3.01. The Borrower declares its commitment to the objectives of the Project. To this end, the Borrower shall carry out Part 1 and Part 3.1 of the Project through MOCPP and Part 2 and Part 3.2 of the Project through MOH in accordance with the provisions of Article V of the General Conditions and Schedule 2 to this Agreement.
Article IV
EFFECTIVENESS; TERMINATION
4.01. The Additional Condition of Effectiveness consists of the following, namely that the Borrower shall adopt a Project Operations Manual (POM) under terms satisfactory to the Bank.
4.02. The Effectiveness Deadline is 90 days after the Signature Date.
Article V
REPRESENTATIVE; ADDRESSES
5.01. The Borrower’s Representative is the Minister in charge of finance.
5.02. For purposes of Section 10.01 of the General Conditions the Borrower’s address is:
Ministry of Finance
Katanciceva 5
10000 Zagreb
Republic of Croatia
Facsimile: (385-1) 4922-598
5.03. For purposes of Section 10.01 of the General Conditions: (a) the Bank’s address is:
International Bank for Reconstruction and Development
1818 H Street, N.W.
Washington, D.C. 20433
United States of America; and
(b) the Bank’s Electronic Address is:
AGREED as of the Signature Date.
Zdravko Marić
Elisabetta Capannelli
SCHEDULE 1
PROJECT DESCRIPTION
The objective of the Project is to assist the Borrower with earthquake reconstruction efforts in Zagreb and the surrounding arreas, improve institutional capacity for reconstructionand strengthen national systems for public health preparedness.
The Project consists of the following parts:
Part 1: Earthquake Recovery and Reconstruction
1. Immediate Public Safety Interventions
Provision of support to carry out the immediate recovery works to ensure safety measures on public and/or private infrastructure damaged as a result of an earthquake in the Borrower’s territory, through carrying out minor civil works for the removal of debris and repair of damaged roofs, chimneys, and other nonstructural elements.
2. Rehabilitation and Reconstruction of Health and Education Facilities
Provision of support to carry out focused rehabilitation and reconstruction of Health and Education Facilities to ensure the continuity of health and education services and to improve resilience to seismic events through, inter alia:
(a) Carrying out of a detailed engineering assessment of selected Health and Education Facilities that were damaged as a result of an earthquake in the Borrower’s territory.
(b) On the basis of the assessment undertaken under (a) above, carrying out of demolition of unsafe public buildings, construction of new public buildings, and rehabilitation and reconstruction of selected public buildings, including services required for the design and supervision of civil works and functional upgrading of said buildings through energy efficiency measures.
(c) Purchasing equipment for Health and Education Facilities that have been damaged as a result of an earthquake in the Borrower’s territory.
3. Housing Reconstruction Support Program Design
(a) Providing technical assistance for the development of the design of a financial support program for medium-term reconstruction of private housing. The technical assistance will focus on data collection and defining options for eligibility criteria, funds flow, oversight structure, as well as social and environmental safeguards.
(b) Carrying out of awareness raising campaigns and outreach activities to attract additional financing to leverage the impact of the housing reconstruction program.
Part 2: Public Health Surveillance and Preparedness
1. Case management and Surveillance
Provision of support to strengthen public health outbreak preparedness including for detection and confirmation, contact tracing, recording, reporting capabilities and surveillance capacity through, inter alia:
(a) Strengthening disease surveillance systems and equipment, public health laboratories, and epidemiological capacity for early detection and confirmation of cases, as well as repairs and rehabilitation of selected public health laboratories’ infrastructure.
(b) Developing systems for active contact tracing and reporting of new cases.
(c) Supporting epidemiological and/or laboratory investigation of selected health conditions.
2. Public Health Preparedness
Provision of support to strengthen the health care system of the Borrower for preparedness planning to provide optimal medical care, maintain essential community services, and minimize risks for patients and health personnel, in part by training health facilities staff and front-line workers on risk mitigation measures and providing them with supplies and equipment to strengthen public health surveillance and support response to future public health outbreaks, through, inter alia:
(a) Providing emergency medical vehicles, medical and laboratory equipment and supplies, medicines, technical assistance and training to public health officials and health care workers, all to strengthen capacity of the health system to respond to public health outbreaks.
(b) Providing personal protective equipment and gear for health care workers and public health rapid response personnel (such as relevant medical specialists, veterinarians, entomologists).
(c) Providing equipment and supplies for telemedicine to monitor and support patients and the health system as needed.
(d) Repurposing and equipping selected health care facilities to deliver critical medical services and cope with increased demand for services in the event of a public health outbreak.
(e) Supporting institutional and organizational restructuring of facilities for the purposes of managing public health outbreaks and training of healthcare staff accordingly, including sector-wide planning activities for medium and long term needs.
Part 3: Project Management
1. Provision of goods, technical assistance, Training, and Operating Costs to support the PIU-1 in the overall day-to-day implementation of Part 1 of the Project, including procurement, financial management, monitoring, and evaluation, carrying out of audits, safeguards and implementation of grievance redress mechanisms, as well as procurement for works for Part 2 of the Project and consolidated reporting for the Project.
2. Provision of goods, technical assistance, Training, and Operating Costs to support the PIU-2 in the overall day-to-day implementation of Part 2 of the Project, including procurement (other than works), financial management, monitoring, and evaluation, carrying out of audits, safeguards and implementation of grievance redress mechanisms.
SCHEDULE 2
PROJECT EXECUTION
Section I.
Implementation Arrangements
A. Institutional Arrangements
1. Without limitation to the provisions of Article V of the General Conditions, and except as the Bank shall otherwise agree, the Borrower shall:
(a) by not later than one (1) month after Effective Date establish and thereafter maintain at all times during the implementation of the Project, a PIU-1, within the MOCPP, with composition, resources, terms of reference and functions acceptable to the Bank. The PIU-1 shall be responsible for the day-to-day implementation of Part 1 of the Project including disbursement, procurement, monitoring and evaluation, consolidated reporting, and ensuring safeguards compliance under the Project as well as procurement for works for Part 2 of the Project, as further elaborated in the Project Operations Manual;
(b) by not later than one (1) month after Effective Date establish and thereafter maintain at all times during the implementation of the Project, a PIU-2, within the MOH, with composition, resources, terms of reference and functions acceptable to the Bank. The PIU-2 shall be responsible for the day-to-day implementation of Part 2 of the Project including disbursement, procurement (other than works), monitoring and evaluation, reporting, and ensuring safeguards compliance under the Project as further elaborated in the Project Operations Manual; and
(c) establish by not later than three months following the Effective Date and thereafter maintain at all times during the implementation of the Project, a high-level Steering Committee, with composition, resources, terms of reference and functions acceptable to the Bank. The Steering Committee shall be responsible for providing strategic guidance, overall oversight of the Project and coordination and monitoring of the Project.
B. Project Operations Manual (POM)
1. The Borrower, through the PIU-1 and PIU-2 respectively, shall carry out the Project, in accordance with POM, satisfactory to the Bank, which shall include the rules, methods, guidelines, standard documents and procedures for the carrying out of the Project, including the following: (a) the detailed description of the Project activities and the institutional arrangements of the Project; (b) the detailed description of prioritization and eligibility criteria for the Project activities; (c) the Project accounting, auditing, reporting, financial, procurement and disbursement procedures; (d) the monitoring indicators for the Project; and (e) the detailed Project costs and financing.