HRVATSKI SABOR
91
Na temelju članka 89. Ustava Republike Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU BROJ F/P 1725 (2010) IZMEĐU REPUBLIKE HRVATSKE I RAZVOJNE BANKE VIJEĆA EUROPE ZA PROJEKT DOGRADNJE I OBNOVE ZATVORA U ZAGREBU
Proglašavam Zakon o potvrđivanju Okvirnog ugovora o zajmu broj F/P 1725 (2010) između Republike Hrvatske i Razvojne banke Vijeća Europe za projekt dogradnje i obnove Zatvora u Zagrebu, koji je Hrvatski sabor donio na sjednici 28. rujna 2012. godine.
Klasa: 011-01/12-01/120
Urbroj: 71-05-03/1-12-2
Zagreb, 4. listopada 2012.
Predsjednik
Republike Hrvatske
Ivo Josipović, v. r.
ZAKON
O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU BROJ F/P 1725 (2010) IZMEĐU REPUBLIKE HRVATSKE I RAZVOJNE BANKE VIJEĆA EUROPE ZA PROJEKT DOGRADNJE I OBNOVE ZATVORA U ZAGREBU
Članak 1.
Potvrđuje se Okvirni ugovor o zajmu broj F/P 1725 (2010) između Republike Hrvatske i Razvojne banke Vijeća Europe za Projekt dogradnje i obnove Zatvora u Zagrebu, potpisan 26. listopada 2011. u Zagrebu i 4. studenog 2011. u Parizu, u izvorniku na engleskom jeziku.
Članak 2.
Tekst Okvirnog ugovora iz članka 1. ovoga Zakona, u izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik, glasi:
F/P 1725 (2010)
FRAMEWORK LOAN AGREEMENT
BETWEEN REPUBLIC OF CROATIA AND COUNCIL OF EUROPE DEVELOPMENT BANK FOR
THE PROJECT EXTENSION AND REHABILITATION OF THE ZAGREB PRISON
The REPUBLIC OF CROATIA, represented by the Ministry of Finance, (hereinafter called the Borrower), on the one hand,
and
The COUNCIL OF EUROPE DEVELOPMENT BANK, International Organisation, Paris (hereinafter called the CEB), on the other hand,
■ Having regard to the application submitted by the Member Government of the Republic of Croatia dated November 3rd, 2010,
■ Having regard to the Third Protocol to the General Agreement on Privileges and Immunities of the Council of Europe,
■ Having regard to CEB’s Overall policy framework for loan and project financing (hereinafter, the Loan Policy),
adopted by CEB Administrative Council’s Resolution 1495 (2006), and
subsequently amended by CEB Administrative Council’s Resolutions 1522
(2009) and 1530 (2010),
■ Having regard to CEB’s Environmental Policy adopted by CEB Administrative Council’s Resolution 1530 (2010) (hereinafter, the Environmental Policy),
■ Having regard to CEB’s Procurement
Guidelines adopted by CEB Administrative Council’s on 21 September 2000
and subsequently amended on 27 October 2004 (hereinafter, the Procurement Guidelines),
■ Having regard to CEB’s Loan Regulations
adopted by CEB Administrative Council’s Resolution 1495 (2006) and
subsequently amended by CEB Administrative Council’s Resolution 1530
(2010) (hereinafter, the Loan Regulations).
HAVE AGREED UPON THE FOLLOWING:
DEFINITIONS
«Allocation of a Tranche»
(hereinafter also «Allocation» or «Allocated») means the commitment of a
Tranche by the Borrower to the component parts of the Project
(identified by means of a standard table appended to this Agreement)
even if such Tranche has not yet been paid out for the Project
«Business Day»
means a day on which the TARGET System (Trans-European Automated
Real-time Gross Settlement Express Transfer System) is operating1
«Closing Date»
means the date from which, upon notification by the CEB to the Borrower,
no further disbursements can be requested by the Borrower
«EURIBOR» (Euro
Interbank Offered Rate) is the rate at which euro interbank term
deposits within the euro zone are offered by one prime bank to another
prime bank. It is sponsored by the European Banking Federation, computed
by Reuters and published every working day in Bruxelles at 11 a.m. on
Reuters page EURIBOR01.
«Final Beneficiaries» are the individuals that benefit from the social effects of the Project
«Modified Following Business Day Convention»
means a convention whereby if a specified date would fall on a day
which is not a Business Day, such date would be the first following day
that is a Business Day unless that day falls in the next calendar month,
in which case that date would be the first preceding day that is a
Business Day
«Project Implementing Agency» (hereinafter called the PIA) means the governmental department/agency who, by delegation of the Borrower, implements and manages the Project
«Project Implementing Unit» (hereinafter called the PIU)
means the unit of project managers in charge, within the PIA, of the
day-to-day implementation, physical and financial management and
follow-up of the project
«Projected State of Progress of Works»
means the ratio of eligible expenditures, for all the component parts
of the Project, to total eligible cost of the project, where eligible
expenditures include already-incurred expenditures as well as those that
are expected to be incurred for a determined period of time not
exceeding one year from the date of the monitoring report (as defined in
Article 4.2.2. below)
«State of Progress of Works»
means the ratio of already-incurred eligible expenditures, on all the
component parts of the Project, to total eligible cost of the project
«Tranche» means an amount disbursed or to be disbursed from the loan
Article 1.
CONDITIONS
This loan is granted under the general
conditions of the Loan Regulations and under the special conditions
established by this framework loan agreement (hereinafter the Agreement), its Appendices and its disbursement agreements (hereinafter the Disbursement Agreements).
Article 2.
THE PROJECT
The CEB grants to the Borrower, who accepts, a loan (hereinafter the Loan)
for the financing of F/P 1725 (2010) approved by CEB’s Administrative
Council on 18 November 2010 and concerning the partial financing of the
extension and rehabilitation of the Zagreb Prison (hereinafter the Project).
The Loan is granted by the CEB in
consideration of the commitment that the Borrower is making (i) to apply
it solely to financing the Project as described in Appendix 1; and (ii)
to carry out the Project under the conditions detailed in Appendix 1.
Any change to the way the Loan is applied
that has not received the CEB’s approval may lead to the suspension,
cancellation or early reimbursement of the Loan, under the terms of
Articles 3.3, 3.5 and 3.6 of the Loan Regulations.
Article 3.
THE LOAN
3.1. Financial conditions
The amount of the Loan granted is:
EUR 6 480 000
Six million four hundred eighty thousand euros
It shall be disbursed in Tranches.
For each Tranche, the amount, the interest
rate, the currency, the disbursement date, the repayment period and each
party’s accounts for remittance, shall be determined jointly by the
Borrower and the CEB.
A Disbursement Agreement which specifies
these conditions shall be drawn up at the time of disbursement
substantially in the form set out in Appendix 2.
3.2. Disbursement
The CEB shall disburse the Loan in a
minimum of two Tranches. The amount of each Tranche shall be determined
according to the State of Progress of Works and/or Projected State of
Progress of Works.
The signature of the Disbursement Agreement
for the first Tranche must occur within 12 months following the entry
into force of the present Agreement, as defined under Article 15; As
conditions precedent for the signature of the Disbursement Agreement for
the first Tranche, the Borrower shall (i) provide evidence, to CEB’s
satisfaction, that a fully functional PIU has been established; and (ii)
submit to CEB for approval a Procurement Plan in accordance with the
requirements specified under Article 4.1.3.
The first Tranche shall not exceed50% of the approved Loan amount.
Each subsequent Tranche can be disbursed
only after the Borrower confirms in writing to the CEB, subject to
compliance with article 4.2.2 below, that 90% of the previous Tranche
has been Allocated. Subsequent Tranches shall be calculated on the basis
of the State of Progress of Works and – if deemed appropriate – of the
Projected State of Progress of Works.
3.3. Closing Date
The Closing Date is 30 June 2014.
3.4. Payment details
All the amounts due by the Borrower under
this Agreement are payable in the currency of each Tranche to the
account number communicated by the CEB to the Borrower at the time of
disbursement.
The Borrower or the bank instructed by the
Borrower, as the case may be, shall send a written payment notice to the
CEB at least five (5) business days before payment of any amounts due
under this Agreement.
Any payment under this Agreement shall be made on a Business Day subject to the Modified Following Business Day Convention.
Article 4.
MONITORING THE LOAN AND THE PROJECT
4.1. Use of the Loan
4.1.1. Period
The Tranches must be Allocated by the Borrower to the Project within twelve (12)months after each disbursement.
The amount not Allocated to the Project within such period must be repaid to the CEB, within thirty (30) days at the latest.
The Borrower undertakes to bear the cost
resulting from this repayment. This cost shall include that which the
CEB will have to bear due to the reinvestment of the same amount on the
date of repayment for the residual life of the original Loan, as well as
any other related cost. The reinvestment rate shall be determined by
the CEB on the basis of market conditions on the repayment date and for
the period in question. The cost shall therefore be calculated taking
into account the difference between the original rate and the
reinvestment rate.
Furthermore, if a Tranche disbursed by the
CEB is not Allocated to the Project or is only partially Allocated to it
within the period mentioned in the first paragraph above, this would
constitute an event as listed in Article 3.3 (h) of Chapter 3 of the
Loan Regulations and may give rise to the suspension, cancellation or
early reimbursement of the Loan under the terms of Articles 3.3, 3.5 and
3.6 of the Loan Regulations.
4.1.2. Implementation of the Project
The Borrower designates the Ministry of
Justice as the PIA. The PIA will establish and maintain within its
structure an appropriately staffed and equipped PIU. Before the first
disbursement, the PIU should be fully functional and adequately staffed
in accordance with CEB’s recommendations during appraisal. However, the
responsibility to comply with all obligations under the Agreement
remains with the Borrower.
4.1.2.1. Duty of care
The Borrower shall apply all care and
diligence, and shall exercise all typically used means, in particular
financial, technical, social, managerial and those concerning
environmental protection, which shall be necessary for the proper
implementation of the Project.
4.1.2.2. Increased or revised cost of the Project
Should the costs of the Project, as
described in Appendix 1 attached hereto, increase or be revised for
whatever reason, the Borrower shall ensure that the additional financial
resources for the completion of the Project are available.
In particular, it shall ensure — before the
Project is implemented — that all the financing, land and real property
rights which are necessary therefor are available and that all assets
and plants are permanently insured and maintained.
In any case, financing by the CEB shall not
exceed 50% of the total cost of the Project, excluding interest and
financial charges, such as defined in Appendix 1.
4.1.2.3. CEB visibility
The Borrower shall (i) indicate in all its
promotional material related to the Project that the latter is partly
financed by the CEB and (ii) consult with CEB regarding the official
press releases about the Project. In any case, information given to the
media, official notices, reports, brochures, billboards or publications
shall display in an appropriate way the CEB logo.
4.1.2.4. Further undertakings
The Borrower shall undertake that:
– The implementation of the Project does
not lead to a violation of the European Convention on Human Rights and
of the European Social Charter;
– The Project complies with CEB’s
Environmental Policy. In particular, the Borrower shall undertake that
the mitigation measures described in the Project’s Environmental
Management Plan (August 2010) elaborated by the Brodarski Institut are
implemented.
4.1.3. Procurement
In accordance with CEB’s Procurement
Guidelines, procurement of goods, works and services under the Project
shall be carried out as follows:
■ Contracts below European Union (EU) thresholds shall be procured in accordance with public procurement legislation in force in the Republic of Croatia.
■ Contracts equal or above the EU
thresholds shall be procured through international (open or restricted)
procedures (requiring publication in the Official Journal of the EU
(«OJEU»)).
The Borrower shall submit to CEB for approval, as indicated under Article 3.2, a Procurement Plan setting forth:
■ contracts for supplies, works, and/or
services required to carry out the Project during the initial period of
at least twelve (12) months;
■ estimated cost of each contract;
■ proposed procurement methods for each contract;
■ estimated launching date of each tender.
After receiving the Procurement Plan, CEB
will inform the Borrower on the related Bank review procedures for each
contract envisaged under the Procurement Plan.
The Borrower shall update the Procurement
Plan annually or as needed throughout the duration of the Project and
submit any relevant update to CEB for approval. The Borrower shall
implement the Procurement Plan in the manner in which it has been
approved by CEB.
The Borrower shall promptly inform the CEB
of any delay, cancellation or contestation and other changes in the
scheduling of the procurement process which could significantly affect
the timely and successful implementation of the Project and agree with
the CEB on corrective measures.