VLADA REPUBLIKE HRVATSKE
34
Na temelju članka 30. stavka 1. Zakona o sklapanju i izvršavanju međunarodnih ugovora (»Narodne novine« broj 28/96), Vlada Republike Hrvatske je na sjednici održanoj 2. svibnja 2013. godine donijela
UREDBU
O OBJAVI IZMJENA I DOPUNA DVOSTRANOG SPORAZUMA O PROJEKTU IZMEĐU VLADE REPUBLIKE HRVATSKE I EUROPSKE KOMISIJE VEZANO UZ SUFINANCIRANJE VELIKOG PROJEKTA »ŽUPANIJSKI CENTAR ZA GOSPODARENJE OTPADOM KAŠTIJUN« CCI BR.: 2008HR16IPR001 U OKVIRU INSTRUMENTA PRETPRISTUPNE POMOĆI (IPA) IPA KOMPONENTA III – REGIONALNI RAZVOJ OPERATIVNI PROGRAM »ZAŠTITA OKOLIŠA« CCI BR.: 2007HR16IPO003
Članak 1.
Objavljuju se Izmjene i dopune Dvostranog sporazuma o projektu između Vlade Republike Hrvatske i Europske komisije vezano uz sufinanciranje velikog projekta »Županijski centar za gospodarenje otpadom KAŠTIJUN« CCI br.: 2008HR16IPR001 u okviru Instrumenta pretpristupne pomoći (IPA) IPA Komponenta III – Regionalni razvoj Operativni program »Zaštita okoliša« CCI br.: 2007HR16IPO003, potpisane u Bruxellesu, 8. siječnja 2013. godine i u Zagrebu, 11. ožujka 2013. godine, u izvorniku na engleskom jeziku.
Članak 2.
Tekst Izmjena i dopuna Dvostranog sporazuma iz članka 1. ove Uredbe, u izvorniku na engleskom jeziku, i u prijevodu na hrvatski jezik glasi:
AMENDING BILATERAL PROJECT AGREEMENT
BETWEEN THE GOVERNMENT OF THE REPUBLIC OF CROATIA AND THE EUROPEAN
COMMISION CONCERNING THE CO-FINANCING OF THE MAJOR PROJECT «COUNTY WASTE
MANAGEMENT CENTRE KAŠTIJUN» CCI NO: 2008HR16IPR001 UNDER THE INSTRUMENT
FOR PRE-ACCESSION ASSISTANCE (IPA) IPA COMPONENT III – REGIONAL
DEVELOPMENT OPERATIONAL PROGRAMME «ENVIRONMENTAL» CCI NO: 2007HR16IPO003
The Government of the Republic of Croatia
and
the European Commission
Having regard to Article 56 of the Financing Agreement,
Having regard to Article 9 of the Bilateral
Project Agreement between the Government of the Republic of Croatia and
the European Commission,
Whereas:
(1) The Treaty of Lisbon entered into force on 1 December 2009.
(2) The Commission Regulation (EC) No
718/2007 of 12 June 2007 implementing Coucil Regulation (EC) No
1085/2006 establishing an instrument for pre-accession assistance (IPA) was last amended by Regulation (EU) No 813/2012 of 12 September 2012.
(3) On 29 November 2007, the Commission
adopted a Decision C(2007)5734 approving the multi-annual operational
programme «Environmental» for EU assistance from the Instrument of
Pre-Accession Assistance for the Regional Development component in the
Republic of Croatia. On 22 June 2010 the Commission adopted Decision
C(2010) 3775, and on 23 October 2012 the Decision C(2012)7401 modifying
the programme.
(4) By Decision C(2009)2584 of 8 April
2009, as amended by Decision C(2011) 1769 of 21 March 2011, the
Commission granted an assistance to the major project «County Waste
Management Centre KAŠTIJUN».
(5) A Bilateral Project Agreement,
regarding the major project «County Waste Management Centre KAŠTIJUN»
forming part of the multi-annual operational programme «Environmental»
2007-2009 was signed on 29 June 2009 between the Government of the
Republic of Croatia and the European Commission as amended on 11 April
2011.
(6) On 20 August 2012, the national
authorities submitted a request for amending this Major Project in which
they requested a change to the maximum IPA contribution due to the
revised funding gap calculation and a minor change in the composition of
the supply equipment.
(7) Decision C(2009) 2584 of 8 April 2009
approving the major project was modified by Decision C(2012) 9481 of
17/12/2012 in order to take the request changes into account.
(8) The Bilateral Agreement should therefore be modified accordingly.
HAS AGREED AS FOLLOWS:
Article 1
The Bilateral Project Agreement signed on 29 June
2009 between the Government of the Republic of Croatia and the European
Commission is amended as follows:
1. Article 2 is amended as follows:
(a) Paragraph 1 is replaced by the following:
«1. The eligible expenditure calculated in
accordance with Article 150 of Regulation (EC) No 718/2007 is set at EUR
29 465 875.»;
(b) Paragraph 2 is replaced by the following:
«2. The co-financing rate for the priority axis 1-
Developing Waste Management Infrastructure of the operational programme
«Environmental» applies to the project. The maximum IPA contribution to
the project is set at EUR 25 045 994.»
2. The Annex is replaced by the Annex to this Agreement.
Article 2
In accordance with Article 9(2) of the Bilateral
Project Agreement, expenditure relating to a physical object introduced
by the modification of a Commission Decision is eligible from the date
of approval of the modification by the Commission.
Article 3
This Agreement is drawn up in duplicate in the English language.
Signed, for and on behalf of the Government of the Republic of Croatia,
at Zagreb, on 11 March 2013
by Hrvoje Dokoza, Deputy Minister in the Ministry of Environmental and Nature Protection
Signed, for and on behalf of the Commission,
at Brussels, on 8 January 2013
by Walter Deffaa
Directeur général
ANNEX
»ANNEX
PHYSICAL OBJECT OF THE MAJOR PROJECT
Operational Programme
«Environmental»
CCI No: 2007HR16IPO003
Project
«County Waste Management Centre KASTIJUN»
CCI No: 2008HR16IPR001
Priority Axis 1:«Developing Waste Management Infrastructure»
Measure 1.1:Establishment of new waste management centres at county/regional level
1. AUTHORITY RESPONSIBLE FOR THE APPLICATION (Operating Structure)
Name: MINISTRY OF ENVIRONMENTAL AND NATURE PROTECTION
Address: Ulica Republike Austrije 14, HR – 10000 ZAGREB
Contact: Mr Hrvoje Dokoza, Deputy Minister, Head of Operating Structure
Telephone: +385 1 3717 272
Fax: + 385 1 3717 149
E-mail: hrvoje.dokoza@mzoip.hr
1.b. FINAL BENEFICIARY (ARTICLE 15 OF THE FINANCING AGREEMENT)
Name: ENVIRONMENTAL PROTECTION AND ENERGY EFFICIENCY FUND
Address: Ksaver 2008, HR – 10 000 Zagreb
Contact: Mr Dinko Polić, Director
Telephone: + 385 1 5391 800
Fax: + 385 1 5391 810
E-mail: kontakt@fzoeu.hr
2. END RECIPIENT OF ASSISTANCE
Name: KASTIJUN Ltd
Address: Forum 1, HR – 52100 Pula
Contact: Mrs Vesna Dukic, Director
Telephone: + 385 52 638 660
Fax: + 385 52 638 662
E-mail: vesna.dukic@kastijun.hr
4. PROJECT LOCATION
3.1. Beneficiary country: Republic of Croatia
3.2. County/province: County of Istria
4. PROJECT DESCRIPTION
A.4.1. General description of the physical object of the project
The project concerns the establishment of
an integrated waste management centre in the County of Istria. It
comprises of the construction of a landfill, a mechanical &
biological treatment (MBT) plant, the construction of six transfer
stations, the development of recycling activities and the closure and
rehabilitation of the existing landfills and dumpsites. Where
appropriate, the extension of the landfill cells will take place.
The construction of two landfill cells
with accompanied facilities and the MBT plant will be co-financed from
the Instrument for Pre-Accession Assistance (IPA). The realisation of
the transfer stations and the closure and rehabilitation of the existing
landfills and dumpsites will be financed from national funds. The
construction of the plant for the production of electricity from biogas
and the potential extension of the landfill will be funded from the gate
fee established at the entrance of the waste management centre.
The project will be constructed adjacent
to the existing Kastijun landfill, 5 km south from the city of Pula, in
the County of Istria with a population of 206.350 inhabitants. It
consists of units of local self-governments, namely 10 towns and 31
municipalities.
The current situation regarding waste
management at the County cannot be described as an integrated one as the
existing seven official landfills are inadequately equipped;
sanitary-technical conditions are unsatisfactory; there is no control
and treatment of landfill gases; fire access roads are missing; exact
data regarding quantities of disposed waste are unavailable; there are
no significant measures for the reduction of the waste produced nor is
there any waste treatment before the disposal of waste.
The project as a whole comprises of four
stages, namely a) preliminary activities such as investigation works,
geotechnical-geological investigations, topographic surveys, permits and
technical designs which are financed from national funds, b) the
construction of two landfill cells with accompanied facilities and a
mechanical and biological treatment plant to be co funded from IPA, c)
the construction of six transfer stations to be financed by national
funds and d) the construction of a power plant and the potential
enlargement of the landfill.
The realisation of all stages of the
project will be essential to ensure an integrated solid waste management
system fully operational to serve the objectives for which is approved
and ensue also its financial viability and sustainability.
Simultaneously, the introduction and development of recycling measures
at County level should be adopted and put in place.
A.4.2. Technical description of the infrastructure investment
The following items of works are co-financed from IPA:
A. Construction of a landfill & a mechanical and biological treatment plant
a.1 The construction of landfill comprises
of two cells. The first cell concerns a bio-reactive landfill cell for
municipal waste with a capacity of 201.700 m³ of waste to be exhausted
in the period 2014-2017. The second one relates to the construction of a
cell for industrial non-hazardous waste with a capacity of 263.095 m³
for the period 2014-2022. Main works include the construction of the
landfill area and its corresponding facilities, namely: terrain
preparation, construction of internal roads, construction of an entrance
and administrative building and of a transport and maintenance centre,
construction of a recycling yards, construction of a waste water
treatment plant, waste water and water supply networks, a leachate
collection system, a degassing system as well as the construction of a
facility for gas treatment (gas flare) as well as all other associated
infrastructure described in project application.
a.2 The construction of a mechanical &
biological treatment plant with accompanying equipment of bio-drying
type with a capacity of 90 000 t where biological & mechanical
techniques of municipal waste treatment are combined in order to produce
Solid Recovered Fuel (SRF), stabilise waste and reduce the volume of
waste for disposal.
B. Equipment
It concerns the purchase of the landfill
and waste management transport equipment. The exact number and precise
nature of this equipment is described in the updated project
application.