HRVATSKI SABOR
124
Na
temelju članka 88. Ustava Republika Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1419 (2001) ZA
OBNOVU ŠKOLE NARODNOG ZDRAVLJA »ANDRIJA ŠTAMPAR« U ZAGREBU I MEĐUNARODNOG
CENTRA ZA ZDRAVSTVENI MANAGEMENT »ANDRIJA ŠTAMPAR« U DUBROVNIKU, IZMEĐU
RAZVOJNE BANKE VIJEĆA EUROPE I REPUBLIKE HRVATSKE
Proglašavam
Zakon o potvrđivanju Okvirnog ugovora o zajmu 1419 (2001) za obnovu Škole
narodnog zdravlja »Andrija Štampar« u Zagrebu i Međunarodnog centra za
zdravstveni management »Andrija Štampar« u Dubrovniku, između Razvojne banke
Vijeća Europe i Republike Hrvatske, koji je donio Hrvatski sabor na sjednici
11. srpnja 2002.
Klasa:
01-081-02-2686/2
Zagreb, 16. srpnja 2002.
Predsjednik
Republike Hrvatske
Stjepan Mesić, v. r.
ZAKON
O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1419 (2001) ZA OBNOVU ŠKOLE
NARODNOG ZDRAVLJA »ANDRIJA ŠTAMPAR« U ZAGREBU I MEĐUNARODNOG CENTRA ZA
ZDRAVSTVENI MANAGEMENT »ANDRIJA ŠTAMPAR« U DUBROVNIKU, IZMEĐU RAZVOJNE BANKE
VIJEĆA EUROPE I REPUBLIKE HRVATSKE
Članak 1.
Potvrđuje se Okvirni ugovor o zajmu 1419
(2001) za obnovu Škole narodnog zdravlja »Andrija Štampar« u Zagrebu i Međunarodnog
centra za zdravstveni management »Andrija Štampar« u Dubrovniku, između Razvojne
banke Vijeća Europe i Republike Hrvatske, potpisan 29. ožujka 2002. u Zagrebu i
Parizu, u izvorniku na engleskom jeziku.
Članak 2.
Tekst ugovora iz članka 1. ovoga Zakona u
izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik glasi:
FRAMEWORK
LOAN AGREEMENT BETWEEN COUNCIL OF EUROPE DEVELOPMENT BANK AND THE REPUBLIC OF
CROATIA
The Council of Europe
Development Bank, Paris, (hereinafter called the »CEB«),
And the Republic of Croatia,(hereinafter called the
»Borrower«),
– Having regard to the application of the Republic of
Croatia dated on December 17, 2001;
– Having regard to the Resolution of the Administrative
Council of the CEB : 1424 (1997) Revised 4 of November 23, 2001;
– Having regard to the Third Additional Protocol to the
General Agreement on Privileges and Immunities of the Council of Europe;
– Having regard to the articles of the Loan Regulations of
the CEB dated October 6, 1970;
HAVE AGREED UPON THE FOLLOWING:
Article
1
This loan is granted under the general
conditions of the current Loan Regulations of the CEB and under the special
conditions fixed by this Framework Loan Agreement and its appendices.
Article
2
THE
PROJECT
The CEB grants to the Borrower, who
accepts, a loan for the partial financing of the F/P 1419 (2001) approved by
the CEBžs Administrative Council on January 30-31, 2002, concerning the
part-financing of the project for the renovation and modernisation of the
»Andrija Stampar« School of Public Health in Zagreb and of the International
Centre for Health Service Management in Dubrovnik, Republic of Croatia.
This
loan is granted by the CEB in consideration of the commitment that the Borrower
is making to apply it solely to financing the project described in Appendix
1, and to carry out such project under
the conditions which are detailed in the said Appendix.
Any
change to the way the loan is applied that has not received the CEBžs approval
may lead to the suspension, cancellation or immediate repayability of the loan,
under the terms of Article 13 of the Loan Regulations.
Article 3
THE LOAN
3.1. Financial
conditions
The amount of the loan granted is up to
the equivalent of:
HRK 21 395 000 Twenty one million three
hundred ninety five thousand Croatian Kunas
The loan shall be disbursed in several
instalments.
Each instalment of the loan shall be for a
period of no more than 10 years, with a 5-year grace period. For each
instalment, the principal, interest rate, currency, duration, disbursement date
and repayment period shall be determined jointly by the Borrower and the CEB
and mutually confirmed by exchange of fax. The account to which the
disbursements shall be paid shall be communicated in due time to the CEB by the
Borrower.
3.2. Disbursement and non-disbursement
fees
A Supplementary Agreement to the present
Framework Loan Agreement, specifying the details of each instalment, will be
determined between the Borrower and the CEB, for each instalment at the time of
its disbursement (Appendix 2).
The disbursement of the loan, in several
instalments, shall be made in accordance with the projectžs work progress.
However, the first disbursement must occur at the latest within 18 months
following the date of approval of the project.
CEB will charge to the Borrower a 0,50%
per annum non-disbursement fee, payable quarterly in arrears, if certain
minimal threshold amounts for the disbursements are not met. Said threshold
amounts are as follows:
(i) If disbursements after 18 months
following project approval represent less than 20% of the total approved loan
amount;
(ii) If disbursements efter 24 months
after project approval represent less than 30% of the total approved loan
amount;
(iii) if disbursements after 36 months
following project approval represent less than 50% of the total approved loan
amount;
3.3. Mobilisation
In order to mobilise the loan instalments,
the Borrower shall send to the CEB in due time a Promissory Note corresponding
to each instalment (Appendix 3).
The Promissory Note is made out and
payable in the currency of the instalment.
3.4. Domicile
All the sums due by the Borrower under
this loan are payable to the CEB in the currency of each instalment to the bank
and account number communicated to the Borrower by the CEB at the time of
disbursement of each instalment, with fax notice to be sent to the CEB by the
Bank charged by the Borrower with payment, at least five working days before
each payment.
3.5. Dates
The provisions of Article 3 are subject to
the agreement »Modified Following Business Day«, the definition of which is to
be found in Appendix 4 to the present Framework Loan Agreement. »Business Day«
means a busines day in the country of the currency and, for disbursements in
EURO, a day on which the Trans-European Automated Real-Time Gross Settlement
Express Transfer (TARGET) System is operating.
Article 4
MONITORING THE LOAN AND THE PROJECT
4.1. Use of the loan
Each instalment must be used by the
Borrower for financing the project within six months after its disbursement by
the CEB.
4.2. Implementation of the project
The
Borrower shall apply all care and diligence, and shall exercise all typically
used means, in particular financial, technical, social, and managerial means
and those concerning environmental protection, which shall be necessary for the
proper implementation of the project.
In
particular, it shall ensure – before the project is implemented – that all the
financing, land and real property rights which are necessary therefor are
available and that all assets and installations are permanently insured and
maintained.
The
Borrower shall undertake, moreover, for each project implemented by a final
beneficiary, that:
–
the final beneficiaries are informed of CEBžs participation in the financing of
the project;
–
the project complies with the relevant Council of Europe conventions;
–
the project respects the environment, on the basis of relevant international
conventions;
–
partial financing by the CEB does not exceed 50% of the total cost of the
project, excluding taxes, interest and financial charges;
–
Procurements will be carried out in accordance with the National Bidding
procedures (Narodne novine N142/97). C.E.B. may allow »domestic preference« in
accordance with, and subject to the following provisions:
•
The local content (labour, raw materials, components or other inputs
originating in the same country as the Borrower) accounts for at least 30
percent of the price of the product of service being tendered for;
•
The margin of preference given by a Borrower to domestic bidders does not
exceed 10 percent;
•
The Bidding Documents clearly indicate the degree of preference, and the
method that would be followed in the evaluation and comparison of bids to give
effect to such preference.
No
domestic preference can be applied without prior approval from the CEB.
In
case the above Procurement Procedures do not apply, the CEB will recommend to
the promoter of private sector projects, whenever appropriate, the use of
competitive bidding procedures, especially for major contracts.
In
any case the responsibility for the implementation of the project, and therefor
for the award and administration of contract under the project, remains with
the Borrower.
The
Borrower must submit to the CEB the final certified copy(ies) of the signed
contract(s) as soon as it (they) is (are) available, and in any case prior to
the second, and subsequent, disbursements. The Borrower will also transmit to
the CEB the report containing the evaluation of the tenders and recommendation
for award and thereafter any proposed extension, modification and the reason
therefore made to the original contract.
4.3. Borroweržs Reports
4.3.1.
Project progress reports
At
least twice a year, from the disbursement of the loan up until the completion
of the entire project, the Borrower shall send to the CEB a report detailing:
–
the state of use of the loan;
–
the progress of the projectžs financing plan;
–
the progress of the projet itself;
–
project management details.
Appendix
5 specifies the model monitoring sheets for the loan and project that must
– as a minimum – be included.
4.3.2.
Project completion report
At the completion of the entire project,
the Borrower shall ensure that the CEB obtains a final report, containing an
appraisal of the projectžs economic, financial, social and environmental
effects.
4.4. Information provision to the CEB
The Borrower shall keep acocunting records
concerning the project, which shall be in conformity with international
standards, and which shall show, at any point, the projectžs state of progress,
and which shall record all operations made, and identify the assets and
services financed with the help of the present loan.
The Borrower undertakes to favourably
receive any information missions carried out by employees of the CEB or outside
consultants hired by the CEB, and to provide all the necessary co-operation for
their information mission, by facilitating any possible visits to the site of
the project. In particular, the CEB may have an on-site audit of the projectžs
accounting carried out by one or more consultants of its choice at the Borroweržs
expence in the case of default by the
Borrower in respect of any of its obligations under the present loan Framework
Loan Agreement.
The Borrower undertakes to respond within
a reasonable period to any request for information from the CEB and to provide
it with any documentation that the CEB should consider necessary for the proper
implementation of the present Framework Loan Agreement, particularly as
concerns monitoring of the project described in Appendix 1 and use of the loan.
The Borrower shall inform the CEB
immediately of any legislative or regulatory amendment in the economic sector
relevant to the project described in Appendix 1, and, in a general sense, of
any event which may have an influence on the execution of its obligations under
the present Framework Loan Agreement.
Any legislative or regulatory amendment in
the economic sector relevant to the project described in Appendix 1, would
constitute an event as listed in Article 13-h of Chapter 3 of the Loan
Regulations of the CEB and may give rise to the suspension, cancellation or
immediate repayability of the loan.
Article 5
THE END OF THE BORROWERžS OBLIGATIONS
The payment of the due amount stipulated
on the Promissory Note releases the Borrower from its obligations as defined in
Article 3 above.
After the full sum of the principal of
this loan, and all interest and other expenses resulting therefrom, in
particular those sums under Articles 6 and 7 below, have been duly paid, the
Borrower shall be fully released from its obligations towards the CEB, with the
exception of those set out in Article 4 above.
Article
6
INTEREST FOR DELAY
Notwithstanding any other recourse
available to the CEB under the present Framework Loan Agreement and the Loan
Regulations of the CEB, or otherwise, if the Borrower does not pay all interest
or any other sum payable under the present Framework Loan Agreement at the
latest on the due date specified, the Borrower must pay additional interest on
the sum due and not fully paid, at the one-month LIBOR rate for the currency of
the late payment as of the due date (if Saturday, Sunday or bank holiday, the
first following working day) at 11 a.m. (local time in London), plus 2.5% per
annum, as of the due date of this sum until the date of actual payment. The applicable
one – month LIBOR rate shall be updated every 30 days.
If an instalment is disbursed in EURO, the
one-month EURIBOR rate will replace the LIBOR rate stated above, fixed at 11:00
a.m. (local time in Brussels), all other conditions remaining unchanged.
Article 7
ASSOCIATED COSTS
All duties and taxes of all kinds, due and
paid, and all expenses resulting either from the conclusion, execution,
liquidation, cancellation or suspension of this Framework Loan Agreement, in
all or in part, or from the guarantee or refinancing of the loan granted,
together with all judicial or extra-judicial deeds having this loan as their
origin, shall be bome by the Borrower.
However, the provisions of Article 25 of
Chapter 4 of the Loan Regulations of the CEB shall apply regarding the costs of
the arbitration procedure mentioned in said Chapter 4.
Article 8
SECURITIES
The Borrower declares that no other
commitment has been made or will be made in the future, which might give a
third party a preferential rank, a preferential right of payment, a collateral
or guarantee of any nature whatsoever which might confer enhanced rights upon
third parties (hereinafter »security«).
If such a security were nevertheless
granted to a third party, the Borrower agrees to form or supply an identical
security in favour of the CEB or, where it is hindered in doing so, an
equivalent security, and to stipulate the formation of such a security in
favour of the CEB.
Failure to comply with these provisions
would represent a case of default as laid down in Article 13-h of Chapter 3 of
the Loan Regulations of the CEB and may give rise to the suspension,
cancellation or immediate repayability of the loan.
Article 9
RELATIONS WITH THIRD PARTIES
The Borrower may not raise any fact
relating, within the scope of the use of the loan, to its relations with third
parties in order to avoid fulfilling, either totally or partially, the
obligations resulting from this Framework Loan Agreement.
The CEB may not be involved in disputes
which might arise between the Borrower and third parties and the costs,
whatever their nature, incurred by the CEB due to any challenge, and in
particular all legal or court costs, shall be at the expense of the Borrower.
Article 10
ENTRY INTO FORCE
This Framework Loan Agreement shall enter
into force on the date on which the Law on its ratification by the Parliament
of the Republic of Croatia will enter into force. The Borrower shall inform the
CEB of the entry into force of the said Law.
Article 11
APPLICABLE LAW