HRVATSKI SABOR
117
Na temelju članka 88. Ustava Republike
Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1351 (1999) ZA
OBNOVU ZDRAVSTVENE INFRASTRUKTURE, IZMEĐU RAZVOJNE BANKE VIJEĆA EUROPE I
REPUBLIKE HRVATSKE
Proglašavam Zakon o potvrđivanju
Okvirnog ugovora o zajmu 1351 (1999) za obnovu zdravstvene infrastrukture,
između Razvojne banke Vijeća Europe i Republike Hrvatske, koji je donio
Hrvatski sabor na sjednici 3. srpnja 2002.
Broj: 01-081-02-2620/2
Zagreb, 8. srpnja 2002.
Predsjednik
Republike Hrvatske
Stjepan Mesić, v. r.
ZAKON
O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1351 (1999) ZA OBNOVU ZRAVSTVENE
INFRASTRUKTURE, IZMEĐU RAZVOJNE BANKE VIJEĆA EUROPE I REPUBLIKE HRVATSKE
Članak 1.
Potvrđuje se Okvirni ugovor o zajmu 1351
(1999) za obnovu zdravstvene infrastrukture, između Razvojne banke Vijeća
Europe i Republike Hrvatske, potpisan 23. listopada 2001. u Zagrebu i 30.
listopada 2001. u Parizu, u izvorniku na engleskom jeziku.
Članak 2.
Tekst Okvirnog ugovora iz članka 1. ovoga
Zakona, u izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik glasi:
FRAMEWORK LOAN AGREEMENT between
COUNCIL OF EUROPE DEVELOPMENT BANK and THE REPUBLIC OF CROATIA
The Council of Europe Development Bank, Paris,
(hereinafter called the »CEB«),
And the Republic of Croatia, (hereinafter called
the »Borrower«), represented by the Ministry of Finance,
• Having regard to the application of the
Republic of Croatia dated on September 10, 1999;
• Having regard to the Resolution of the
Administrative Council of the CEB : 1424 (1997) Revised;
• Having regard to the Third Protocol to the
General Agreement on Privileges and Immunities of the Council of Europe;
• Having regard to the articles of the Loan
Regulations of the CEB dated October 6, 1970.
HAVE AGREED UPON THE FOLLOWING:
Article 1
This
loan is granted under the general conditions of the current Loan Regulations of
the CEB and under the special conditions fixed by this agreement and its
appendices.
Article
2: THE PROJECT
The CEB grants to the Borrower, who
accepts, a loan for the partial financing of the F/P 1351 (1999) approved by
the CEBžs Administrative Council on July 5 - 9, 2000, and as modified on
September 21, 2000, concerning the part-financing of rehabilitation and
purchase of equipment for the benefit of hospital services throughout the
territory of Croatia.
This
loan is granted by the CEB in consideration of the commitment that the Borrower
is making to apply it solely to financing the project described in Appendix 1,
and to carry out such project under the conditions which are detailed in the
said Appendix.
Any
change to the way the loan is applied that has not received the CEBžs approval
may lead to the suspension, cancellation or immediate repayability of the loan,
under the terms of Article 13 of the Loan Regulations.
Article 3: THE
LOAN
3.1 Financial conditions
The
amount of the loan granted is up to the equivalent of:
HRK
186 837 031
One
hundred eighty six million eight hundred thirty seven thousand thirty one
Croatian kunas
The
loan shall be disbursed in several instalments.
Each
instalament of the loan shall be for a period of no more than 10 years, with a
5-year grace period. The amount, interest rate, currency, duration,
disbursement date, repayment period, and each partyžs account for remittance
shall be determined jointly by the Borrower and the CEB, and mutually confirmed
by exchange of fax.
The
interest rate for each loan instalment will be subsidised through CEBžs
Selective Trust Account. This subsidy cannot exceed EUR 685 555 for the total
amount of the project approved by CEBž Administrative Council. The subsidy has
been calculated at 34 basis points per annum (0.34%) on the basis of a loan
with a 10-year tenor including a 5 year grace period. However, in case the
interest rate before subsidising would be below the rate of subsidy, the
subsidy shall be equivalent to that rate.
3.2. Disbursement
A
Supplementary Agreement to the present Framework Loan Agreement, specifying the
details of each instalment, will be established between the Borrower and the
CEB, for each instalment at the time of its disbursement (Appendix 2).
3.3. Mobilisation
In
order to mobilise the loan instalments, the Borrower shall send to the CEB in
due time a Promissory Note corresponding to each instalment (Appendix 3A and
3B).
The
Promissory Note is made out and payable in the currency of the instalment.
3.4. Domicile
All
the sums due by the Borrower under this loan are payable to the CEB in the
currency of each instalment to the bank and account number communicated to the
Borrower by the CEB at the time of disbursement of each instalment, with fax
notice to be sent to the CEB by the bank charged by the Borrower with payment,
at least five working days before each payment.
3.5. Dates
The
provisions of Article 3 are subject to the agreement »Modified Following
Business Day«, the definition of which is to be found in Appendix 4 to the
present agreement (»Business Day« in the country of the currency). For
disbursements in EURO; »Business Day« means the day on which the Trans-European
Automated Real-Time Gross Settlement Express Transfer (TARGET) System is
operating.
Article 4:
MONITORING THE LOAN AND THE PROJECT
4.1. Use of the
loan
Each
instalment must be used by the Borrower for financing the project within six
months after its disbursement by the CEB.
4.2.
Implementation of the project
The
Borrower shall apply all care and diligence, and shall exercise all typically
used menas, in particular financial, technical, social, and managerial means
and those concerning environmental protection, which shall be necessary for the
proper implementation of the project.
In
particular, it shall ensure – before the project is implemented – that all the
financing, land and real property rights which are necessary therefor are
available and that all assets and installations are permanently insured and
maintained.
The
Borrower shall undertake, moreover, that:
–
the project complies with the relevant Council of Europe conventions;
–
the project respects the environment, on the basis of relevant international
conventions;
–
partial financing by the CEB does not exceed 50% of the total cost of the
project, excluding taxes, interest and financial charges.
–
investments higher than the counter-value of 10 million EUR shall be subject to
international calls for tender.
4.3.
Borroweržs Reports
4.3.1.
Project progress reports
At
least twice a year, from the date of the first disbursement of the loan up until
the completion of the entire project, the Borrower shall send to the CEB a
report detailing:
–
the state of use of the loan;
–
the progress of the projectžs financing plan;
–
the progress of the project itself;
–
project management details.
Appendix
5 specifies the model monitoring sheets for the loan and the project that must
– as a minimum – be included.
4.3.2.
Project completion report
At
the completion of the entire project, the Borrower shall ensure that the CEB
obtains a final report, containing an appraisal of the projectžs economic,
financial, social and environmental effects.
4.4.
Information provision to the CEB
The
Borrower shall keep accounting records, concerning the project, which shall be
in conformity with international standards and which shall show, at any point,
the projectžs state of progress, and which shall record all operations made,
and identify the assets and services financed with the help of the present
loan.
The
Borrower undertakes to favourably receive any information missions carried out
by employees of the CEB or outside consultants hired by the CEB, and to provide
all the necessary co-operation for their information mission, by facilitating
any possible visits to the site of the project. In particular, the CEB may have
an on-site audit of the projectžs accounting carried out by one or more
consultants of its choice at the Borroweržs expense in the case of default by
the Borrower in respect of any of its obligations under the present loan
agreement.
The
Borrower undertakes to respond within a reasonable period to any request for
information from the CEB and to provide it with any documentation that the CEB
should consider necessary for the proper implementation of the present
agreement, particularly as concerns monitoring of the project described in
Appendix 1 and use of the loan.
The
Borrower shall inform the CEB immediately of any legislative or regulatory
amendment in the economic sector relevant to the project described in Appendix
1, and, in a general sense, of any event which may have an influence on the
execution of their obligations under the present agreement.
Any
legislative or regulatory amendment in the economic sector relevant to the
project described in Appendix 1, would constitute an event as listed in Article
13-h of Chapter 3 of the Loan
Regulations of the CEB and may give rise to the suspension, cancellation or
immediate repayability of the loan.
Article
5: THE END OF THE BORROWERžS OBLIGATIONS
The
payment of the due amount stipulated on the Promissory Note releases the
Borrower from its obligations as defined in Article 3 above.
After
the full sum of the principal of this loan, and all interest and other expenses
resulting therefrom, in particular those sums under Articles 6 and 7 below,
have been duly paid, the Borrower shall be fully released from its obligations
towards the CEB, with the exception of those set out in Article 4 above.
Article
6: INTEREST FOR DELAY
Notwithstanding
any other recourse available to the CEB under the present agreement and the
Loan Regulations, or otherwise, if the Borrower does not pay all interest or
any other sum payable under the present agreement at the latest on the due date
specified, the Borrower must pay additional interest on the sum due and not
fully paid, at the one-month LIBOR rate for the currency of the late payment as
of the due date (if Saturday, Sunday or bank holiday, the first following
working day) at 11 a.m. (local time in London), plus 2.5% per annum, as of the
due date of this sum until the date of actual payment. The applicable one month
LIBOR rate shall be updated every 30 days.
If
an instalment is disbursed in EURO, the one-month EURIBOR rate will replace the
LIBOR rate stated above, fixed at 11:00 a.m. (local time in Brussels), all
other conditions remaining unchanged.
Article
7: ASSOCIATED COSTS
All
duties and taxes of all kinds, due and paid, and all expenses resulting either
from the conclusion, execution, liquidation, cancellation or suspension of this
agreement, in all or in part, or from the guarantee or refinancing of the loan
granted, together with all judicial or extra-judicial deeds having this loan as
their origin, shall be borne by the Borrower.
However,
the provisions of Article 25 of Chapter 4 of the Loan Regulations of the CEB
shall apply regarding the costs of the arbitration procedure mentioned in said
Chapter 4.
Article 8:
SECURITIES
The
Borrower declares that no other commitment has been made or will be made in the
future, which might give a third party a preferential rank, a preferential
right of payment, a collateral or guarantee of any nature whatsoever which
might confer enhanced rights upon third parties (hereinafter »security«).
If
such a security were neverthaless granted to a third party, the Borrower agrees
to form or supply an identical security in favour of the CEB or, where it is
hindered in doing so, an equivalent security, and to stipulate the formation of
such a security in favour of the CEB.
Failure
to comply with these provisions would represent a case of default as laid down
in Article 13-h of Chapter 3 of the Loan Regulations of the CEB and may give
rise to the suspension, cancellation or immediate repayability of the loan.
Article 9: REALTIONS WITH THIRD PARTIES
The
Borrower may not raise any fact relating, within the scope of the use of the
loan, to its relations with third parties in order to avoid fulfilling, either
totally or partially, the obligations resulting from this agreement. The CEB may not be involved in disputes which
might arise between the Borrower and third parties and the costs, whatever
their nature, incurred by the CEB due to any challenge, and in particular all
legal or court costs, shall be at the expense of the Borrower.
Article 10: ENTRY INTO FORCE
This
Framework Loan Agreement shall enter into force upon ratification by the
Parliament of the Republic of Croatia.
Article 11: APPLICABLE LAW
This
agreement and the negotiable securities relating thereto shall be governed by
the rules of the CEB as specified in the provisions of Article 1, paragraph 3,
of the Third Additional Protocol dated 6 March 1959 to the General Agreement on
Privileges and Immunities of the Council of Europe dated 2 September 1949 and,
secondarily, if necessary, by French law.
Disputes between the parties to this agreement shall be subject to
arbitration under the conditions laid down in Chapter 4 of the Loan Regulations
of the CEB.
Article 12: INTERPRETATION OF THE
AGREEMENT