HRVATSKI SABOR
135
Na temelju članka 88. Ustava Republike Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1379 (2000) ZA
OBNOVU FRANJEVAČKOG SAMOSTANA MALE BRAĆE U DUBROVNIKU, IZMEĐU RAZVOJNE BANKE
VIJEĆA EUROPE I REPUBLIKE HRVATSKE
Proglašavam Zakon o potvrđivanju Okvirnog ugovora o zajmu 1379 (2000)
za obnovu Franjevačkog samostana Male braće u Dubrovniku, između Razvojne
banke Vijeća Europe i Republike Hrvatske, koji je donio Hrvatski sabor na
sjednici 7. prosinca 2001.
Broj: 01-081-01-3896/2
Zagreb, 13. prosinca 2001.
Predsjednik
Republike Hrvatske
Stjepan Mesić, v. r.
ZAKON
O POTVRĐIVANJU OKVIRNOG UGOVORA O ZAJMU 1379 (2000) ZA OBNOVU FRANJEVAČKOG
SAMOSTANA MALE BRAĆE U DUBROVNIKU, IZMEĐU RAZVOJNE BANKE VIJEĆA EUROPE I
REPUBLIKE HRVATSKE
Članak 1.
Potvrđuje se Okvirni ugovor o zajmu 1379 (2000) za obnovu Franjevačkog
samostana Male braće u Dubrovniku, između Razvojne banke Vijeća Europe i
Republike Hrvatske, potpisan 19. lipnja 2001. u Dubrovniku, u izvorniku na
engleskom jeziku.
Članak 2.
Tekst Okvirnog ugovora iz članka 1. ovoga Zakona, u izvorniku na
engleskom jeziku i u prijevodu na hrvatski jezik glasi:
FRAMEWORK LOAN AGREEMENT BETWEEN COUNCIL
OF EUROPE DEVELOPMENT BANK AND THE REPUBLIC OF CROATIA
The
Council of Europe Development Bank, Paris, (hereinafter called the »CEB«),
And
the Republic of Croatia, (hereinafter called the »Borrower«),
•
Having regard to the application of the Republic of Croatia dated on December
19, 2000;
•
Having regard to the Resolution of the Administrative Council of the CEB : 1424
(1997) Revised 3 of November 24, 2000;
•
Having regard to the Third Additional Protocol to the General Agreement on
Privileges and Immunities of the Council of Europe;
•
Having regard to the articles of the Loan Regulations of the CEB dated October
6, 1970.
HAVE
AGREED UPON THE FOLLOWING:
Article 1
This loan is granted under the general
conditions of the current Loan Regulations of the CEB and under the special
conditions fixed by this agreement and its appendices.
Article 2:
THE PROJECT
The CEB grants
to the Borrower, who accepts, a loan for the partial financing of the F/P 1379
(2000) approved by the CEBžs Administrative Council on January 25–26, 2001,
concerning the part-financing of the project for the restoration of the
Franciscan Monastery »Mala Braca« in Dubrovnik, Republic of Croatia.
This loan is
granted by the CEB in consideration of the commitment that the Borrower is
making to apply it solely to financing the project described in Appendix 1, and
to carry out such project under the conditions which are detailed in the said
Appendix.
Any change to
the way the loan is applied that has not received the CEBžs approval may lead
to the suspension, cancellation or immediate repayability of the loan, under
the terms of Article 13 of the Loan Regulations.
Article
3:
THE
LOAN
3.1. Financial conditions
The amount of the loan granted is up to
the equivalent of:
HRK
10 325 454
Ten
million three hundred twenty five thousand four hundred fifty four Croatian
Kunas
The loan shall be disbursed in several
instalments.
Each instalment of the loan shall be for a
period of no more than 10 years, with a 5-year grace period. The principal,
interest rate, currency, duration and disbursement date shall be decided by
mutual agreement, for each instalment, between the Borrower and the CEB, by
fax. The account to which the disbursements shall be paid shall be communicated
in due time to the CEB by the Borrower.
3.2. Disbursement and non-disbursement
fees
A Supplementary Agreement to the present
Framework Loan Agreement, specifying the details of each instalment, will be
determined between the Borrower and the CEB, for each instalment at the time of
its disbursement (Appendix 2).
The disbursement of the loan, in several
instalments, shall be made in accordance with the projectžs work progress.
However, the first disbursement must occur at the latest within 18 months
following the date of approval of the project.
CEB will charge to the Borrower a 0.50%
per annum non-disbursement fee, payable quarterly in arrears, if certain minimal
threshold amounts for the disbursements are not met. Said threshold amounts are
as follows:
(i) If disbursements after 18 months
following project approval represent less than 20% of the total approved loan
amount;
(ii) If disbursements after 24 months
after project approval represent less than 30% of the total approved loan
amount;
(iii) If disbursements after 36 months
following project approval represent less than 50% of the total approved loan
amount;
3.3. Mobilisation
In order to mobilise the loan instalments,
the Borrower shall send to the CEB in due time a Promissory Note corresponding
to each instalment (Appendix 3).
The Promissory Note is made out and
payable in the currency of the instalment.
3.4. Domicile
All the sums due by the Borrower under
this loan are payable to the CEB in the currency of each instalment to the bank
and account number communicated to the Borrower by the CEB at the time of
disbursement of each instalment, with fax notice to be sent to the CEB by the
Bank charged by the Borrower with payment, at least five working days before
each payment.
3.5. Dates
The provisions of Article 3 are subject to
the agreement »Modified Following Business Day«, the definition of which is to
be found in Appendix 4 to the present agreement (»Business Day« in the country
of the currency). For disbursements in EURO, »Business Day« means the day on
which the Trans-European Automated Real-Time Gross Settlement Express Transfer
(TARGET) System is operating.
Article 4:
MONITORING THE LOAN AND THE PROJECT
4.1. Use of the loan
Each instalment must be used by the
Borrower for financing the project within six months after its disbursement by
the CEB.
4.2. Implementation of the project
The Borrower shall apply all care and
diligence, and shall exercise all typically used means, in particular
financial, technical, social, and managerial means and those concerning
environmental protection, which shall be necessary for the proper
implementation of the project.
In particular, it shall ensure – before
the project is implemented – that all the financing, land and real property
rights which are necessary therefor are available and that all assets and
installations are permanently insured and maintained.
The Borrower shall undertake, moreover,
that:
– the project complies with the relevant
Council of Europe conventions;
– the project respects the environment, on
the basis of relevant international conventions;
– partial financing by the Fund does not
exceed 50% of the total cost of the project, excluding taxes, interest and
financial charges.
– Procurements will be carried out in
accordance with the National Bidding procedures (Narodne novine N142/97) In
case the above Procurement Procedures do not apply, the CEB will recommend to
the promoter of private sector projects, whenever appropriate, the use of
competitive bidding procedures, especially for major contracts.
4.3. Borroweržs
Reports
4.3.1. Project progress reports
At least twice a year, from the
disbursement of the loan up until the completion of the entire project, the
Borrower shall send to the CEB a report detailing:
– the state of use of the loan;
– the progress of the projectžs financing
plan;
– the progress of the project itself;
– project management details.
Appendix 5 specifies the model monitoring
sheets for the loan and the project that must – as a minimum – be included.
4.3.2. Project completion report