Tekst izvorne objave
NN-MU 14/2002Sažetak
Potvrđuje se Ugovor o jamstvuizmeđu Republike Hrvatske i Europske banke za obnovu i razvoj za Projekt Centraza oblasnu kontrolu Zagreb, potpisan 5. rujna 2002. u Zagrebu, u izvorniku naengleskom jeziku.
Međunarodni ugovor
Potvrđuje se Ugovor o jamstvuizmeđu Republike Hrvatske i Europske banke za obnovu i razvoj za Projekt Centraza oblasnu kontrolu Zagreb, potpisan 5. rujna 2002. u Zagrebu, u izvorniku naengleskom jeziku.
HRVATSKI SABOR
166
Na temelju članka 88. Ustava Republike Hrvatske, donosim
ODLUKU
O PROGLAŠENJU ZAKONA O POTVRĐIVANJU UGOVORA O JAMSTVU IZMEĐU REPUBLIKE HRVATSKE I EUROPSKE BANKE ZA OBNOVU I RAZVOJ ZA PROJEKT CENTRA ZA OBLASNU KONTROLU ZAGREB
Proglašavam Zakon o potvrđivanju Ugovora o jamstvu između Republike Hrvatske i Europske banke za obnovu i razvoj za Projekt Centra za oblasnu kontrolu Zagreb, koji je donio Hrvatski sabor za sjednici 7. studenoga 2002.
Broj: 01-081-02-3535/2
Zagreb, 11. studenoga 2002.
Predsjednik
Republike Hrvatske
Stjepan Mesić, v. r.
ZAKON
O POTVRĐIVANJU UGOVORA O JAMSTVU IZMEĐU REPUBLIKE HRVATSKE I EUROPSKE BANKE ZA OBNOVU I RAZVOJ ZA PROJEKT CENTRA ZA OBLASNU KONTROLU ZAGREB
Članak 1.
Potvrđuje se Ugovor o jamstvu između Republike Hrvatske i Europske banke za obnovu i razvoj za Projekt Centra za oblasnu kontrolu Zagreb, potpisan 5. rujna 2002. u Zagrebu, u izvorniku na engleskom jeziku.
Članak 2.
Tekst Ugovora iz članka 1. ovoga Zakona, u izvorniku na engleskom jeziku i u prijevodu na hrvatski jezik glasi:
GUARANTEE AGREEMENT (ZAGREB AREA CONTROL CENTRE PROJECT) between THE REPUBLIC OF CROATIA and EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT
GUARANTEE AGREEMENT
AGREEMENT dated 5th September 2002 between THE REPUBLIC OF CROATIA (the »Guarantor«) and EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT (the »Bank«).
PREAMBLE
WHEREAS, the Guarantor and Croatia Control Limited have requested assistance from the Bank in the financing of part of the Project;
WHEREAS, pursuant to a loan agreement dated the date hereof between Hrvatske kontrole zračne plovidbe, d.o.o. as Borrower and the Bank (the »Loan Agreement« as defined in the Standard Terms and Conditions), the Bank has agreed to make a loan to the Borrower in the amount of € 25,000,000, subject to the terms and conditions set forth or referred to in the Loan Agreement, but only on the condition that the Guarantor guarantees the obligations of the Borrower under the Loan Agreement as provided in this Agreement; and
WHEREAS, the Guarantor, in consideration of the Bank entering into the Loan Agreement with the Borrower, has agreed to guarantee such obligations of the Borrower.
NOW, THEREFORE,the parties hereby agree as follows:
Article I - STANDARD TERMS AND CONDITIONS; DEFINITIONS
Section 1.01. Incorporation of Standard Terms and Conditions
All of the provisions of the Bankžs Standard Terms and Conditions dated February 1999 are hereby incorporated into and made applicable to this Agreement with the same force and effect as if they were fully set forth herein.
Section 1.02. Definitions
Wherever used in this Agreement (including the Preamble), unless stated otherwise or the context otherwise requires, the terms defined in the Preamble have the respective meanings given to them therein, the terms defined in the Standard Terms and Conditions and the Loan Agreement have the respective meanings given to them therein and the following term has the following meaning:
»Guarantoržs Authorised
Representative« means the Minister of Finance of the Guarantor.
Section 1.03. Interpretation
In this Agreement, a reference to a specified Article or Section shall, except where stated otherwise in this Agreement, be construed as a reference to that specified Article or Section of this Agreement.
Article II - GUARANTEE; OTHER OBLIGATIONS
Section 2.01. Guarantee
The Guarantor hereby unconditionally guarantees, as primary obligor and not as surety merely, the due and punctual payment of any and all sums due under the Loan Agreement, whether at stated maturity, by acceleration or otherwise, and the punctual performance of all other obligations of the Borrower, all as set forth in the Loan Agreement.
Section 2.02. Project Completion
Whenever there is reasonable cause to believe that the funds available to the Borrower will be inadequate to meet the estimated expenditures required for the carrying out of the Project, the Guarantor shall promptly take measures satisfactory to the Bank to provide the Borrower, or cause the Borrower to be provided, with such funds as are needed to meet such expenditures and requirements.
Section 2.03. Other Obligations
Without limiting the generality of any other provisions of this Agreement or the Standard Terms and Conditions, the Guarantor shall:
(a) maintain the full benefit to the Borrower of air navigation charges paid by users for the navigation services provided by the Borrower, without retention or offset to the state budget;
(b) maintain the Borrower as a limited liability company; and
(c) not take any action (including by subdivisions of the Guarantor or entities owned or controlled by the Guarantor) which would prevent or interfere with the execution of the Project or any obligations under the Loan Agreement.
Article III - MISCELLANEOUS
Section 3.01. Notices
The following addresses are specified for purposes of Section 10.01 of the Standard Terms and Conditions:
For the Guarantor:
Minister of Finance of the Republic of Croatia
Katanciceva 5
10000 Zagreb
Croatia
Attention: Minister of Finance of the Republic of Croatia
Fax: + 385 1 4591248
For the Bank:
European Bank for Reconstruction and Development
One Exchange Square
London EC2A 2JN
United Kingdom
Attention: Operation Administration Unit
Fax: +44-20-7338-6100
Telex: 8812161
Answerback: EBRD L G
Section 3.02. Legal Opinion
For purposes of Section 9.03(b) of the Standard Terms and Conditions and in accordance with Section 6.02 of the Loan Agreement, the opinion or opinions of counsel shall be given on behalf of the Guarantor by the Minister of Justice.
IN WITNESS WHEREOF the parties hereto, acting through their duly authorised representatives, have caused this Agreement to be signed in four copies and delivered at [London, England] as of the day and year first above written.
REPUBLIC OF CROATIA
By:
Name: Damir Kuštrak
Title: Deputy Finance Minister
EUROPEAN BANK
FOR RECONSTRUCTION AND DEVELOPMENT
By:
Name: Riccardo Puliti
Title: Deputy Director
UGOVOR O JAMSTVU (PROJEKT
CENTRA ZA OBLASNU KONTROLU ZAGREB) IZMEĐU
REPUBLIKE HRVATSKE I EUROPSKE BANKE ZA OBNOVU I RAZVOJ
UGOVOR O JAMSTVU
UGOVOR O JAMSTVU od 5. rujna 2002. između REPUBLIKE HRVATSKE (»Jamac«) i EUROPSKE BANKE ZA OBNOVU I RAZVOJ (»Banka«).
PREAMBULA
BUDUĆI DA su Jamac i Hrvatska kontrola zračne plovidbe d.o.o. zatražili pomoć od Banke za financiranje dijela Projekta;
BUDUĆI DA je u skladu s Ugovorom o zajmu između Hrvatske kontrole zračne plovidbe d.o.o. kao Zajmoprimca i Banke (»Ugovor o zajmu« kako je definiran u Standardnim uvjetima) koji je sklopljen istog dana kada i ovaj Ugovor o jamstvu, Banka spremna odobriti Zajmoprimcu zajam u iznosu od 25,000,000 EUR, po uvjetima koji su određeni ili se navode u Ugovoru o zajmu, ali samo pod uvjetom da je jamac suglasan jamčiti za obveze Zajmoprimca po Ugovoru o zajmu, kako je navedeno ovim Ugovorom; i
BUDUĆI DA je Jamac suglasan, u odnosu na sklapanje Ugovora o zajmu između Banke i Zajmoprimca, jamčiti za obveze Zajmoprimca po istom.
U SKLADU S NAVEDENIM, ugovorne strane ugovaraju kako slijedi:
Članak I. – STANDARDNI UVJETI; DEFINICIJE
Odlomak 1.01. Primjena standardnih uvjeta
Sve odredbe Standardnih uvjeta Banke iz veljače 1999. godine ovime postaju sastavni dio ovog Ugovora o jamstvu i primjenjuju se u odnosu na isti, te su pravovaljane i na snazi kao da su u cijelosti navedene u istom.
Odlomak 1.02. Definicije
Kad su upotrijebljeni u ovom Ugovoru (uključujući i Preambulu), osim ako nije drugačije navedeno ili ako kontekst ne zahtijeva drugačije, pojmovi definirani u Preambuli imaju značenja koja su im pripisana u Preambuli, pojmovi definirani u Standardnim uvjetima i Ugovoru o zajmu imaju značenja koja su im pripisana u tim dokumentima, a pojam definiran u nastavku ima sljedeće značenje:
»Ovlašteni zastupnik Jamca« znači ministar financija Jamca.
Odlomak 1.03. Tumačenje
U ovom Ugovoru, odnošenje na određeni članak ili odlomak, osim ako nije drugačije navedeno u ovom Ugovoru, tumačit će se kao odnošenje na taj određeni članak ili odlomak ovog Ugovora.
Članak II – JAMSTVO; OSTALE OBVEZE
Odlomak 2.01. Jamstvo
Jamac ovime bezuvjetno jamči, kao primarni dužnik, a ne samo kao jamac, za uredno i pravodobno plaćanje svakog i svih iznosa koji dospijevaju po Ugovoru o zajmu, bilo po utvrđenim ili prijevremenim dospijećima, te za pravodobno izvršavanje svih drugih obveza Zajmoprimca, u skladu s Ugovorom o zajmu.
Odlomak 2.02. Dovršenje projekta
Kad god postoji opravdan razlog za mišljenje da sredstva dostupna Zajmoprimcu neće biti dostatna za podmirenje procijenjenih rashoda potrebnih za dovršenje Projekta, Jamac će pravodobno poduzeti mjere zadovoljavajuće za Banku kako bi Zajmoprimcu osigurao, ili će prouzročiti da se Zajmoprimcu osiguraju sredstva potrebna za podmirenje takvih rashoda i potreba.
Odlomak 2.03. Ostale obveze
Ne ograničavajući općenitost drugih odredbi ovog Ugovora ili Standardnih uvjeta, Jamac:
(a) će osigurati Zajmoprimcu puni iznos naknada za zračnu navigaciju koju plaćaju korisnici za navigacijske usluge koje pruža Zajmoprimac, bez zadržavanja ili prijeboja u korist državnog proračuna.
(b) će zadržati Zajmoprimca kao društvo s ograničenom odgovornošću; i
(c) neće poduzeti nikakvu radnju (uključivši od strane podrazdjela Jamca ili tijela u vlasništvu ili kontroliranih od strane Jamca) koja bi onemogućila ili spriječila izvršenje Projekta ili bilo kojih obveza po Ugovoru o zajmu.
Članak III – RAZNO
Odlomak 3.01. Obavijesti
Niže navedene adrese služe za namjene iz Odlomka 10.01 Standardnih uvjeta:
Za Jamca:
Ministarstvo financija Republike Hrvatske
Katančićeva 5
10000 Zagreb
Republika Hrvatska
Na znanje: Ministar financija Republike Hrvatske
Telefaks: +385 1 459 1248
Za Banku:
European Bank for Reconstruction and Development
One Exchange Square
London EC2A 2JN
United Kingdom
Attention: Operation Administration Unit
Fax: +44-20-7338-6100
Telex: 8812161
Answerback:EBRD L G
Odlomak 3.02. Pravno mišljenje
U svrhu Odlomka 9.03(b) Standardnih uvjeta i u skladu sa Odlomkom 6.02. Ugovora o zajmu, Ministarstvo pravosuđa izdat će mišljenje ili mišljenja pravnika za Jamca.
U POTVRDU NAVEDENOGA, ugovorne strane putem svojih uredno ovlaštenih zastupnika, potpisuju ovaj Ugovor u četiri primjerka i sklapaju ga u Zagrebu, Republici Hrvatskoj na naprijed navedeni datum.
REPUBLIKA HRVATSKA
Ime: Damir Kuštrak
Funkcija: zamjenik ministra financija
EUROPSKA BANKA
ZA OBNOVU I RAZVOJ
Ime: Riccardo Puliti
Funkcija: zamjenik direktora
LOAN AGREEMENT
(ZAGREB AREA CONTROL CENTRE PROJECT) between HRVATSKA
KONTROLA ZRAČNE PLOVIDBE d.o.o. and EUROPEAN BANK FOR RECONSTRUCTION
AND DEVELOPMENT
LOAN AGREEMENT
AGREEMENT dated 5th September 2002 between HRVATSKA KONTROLA ZRAČNE PLOVIDBE d.o.o. (the »Borrower«) and EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT (the »Bank«).
PREAMBLE
WHEREAS, the Bank has been established to provide financing for specific projects to foster the transition towards open market‑oriented economies and to promote private and entrepreneurial initiative in the Central and Eastern European countries committed to and applying the principles of multiparty democracy, pluralism and market economics;
WHEREAS, the Borrower intends to implement the Project as described in Schedule 1 which is designed to assist the Borrower in modernising the Zagreb Area Control Centre.
WHEREAS, the Republic of Croatia and the Borrower have requested assistance from the Bank in financing part of the Project;
WHEREAS, the Borrower intends to contract a loan from the European Investment Bank (the »Co-lender« or »EIB«) in the amount of € 20,000,000 to assist in financing Parts B and C of the Project, subject to the terms and conditions to be set forth in an agreement (the »Co-financing Agreement«) between the Borrower and the Co-lender;
WHEREAS, pursuant to a guarantee agreement dated the date hereof between the Republic of Croatia as Guarantor and the Bank (the »Guarantee Agreement« as defined in the Standard Terms and Conditions), the Guarantor has guaranteed the obligations of the Borrower under this Agreement; and
WHEREAS, the Bank has agreed on the basis of, inter alia, the foregoing to make a loan to the Borrower in the amount of € 25,000,000 subject to the terms and conditions set forth or referred to in this Agreement.
NOW, THEREFORE, the parties hereby agree as follows:
Article I - STANDARD TERMS AND CONDITIONS; DEFINITIONS
Section 1.01. Incorporation of Standard Terms and Conditions
All of the provisions of the Bankžs Standard Terms and Conditions dated February 1999 are hereby incorporated into and made applicable to this Agreement with the same force and effect as if they were fully set forth herein, subject, however, to the following modifications (such provisions as so modified are hereinafter called the »Standard Terms and Conditions«):
(a) The definition of »Business Day« in Section 2.02 of the Bankžs Standard Terms and Conditions dated February 1999 shall, for purposes of this Agreement, be modified to read as follows:
»Business Day« means a day on which the Trans-European Automated Real-Time Gross Settlement Express Transfer (TARGET) System is open.«
(b) The definition of »Unwinding Costs« in Section 2.02 of the Bankžs Standard Terms and Conditions dated February 1999 shall, for purposes of this Agreement, be modified to read as follows:
»Unwinding Costs« means the amount by which the Original Income Stream exceeds the Substitute Income Stream, where:
(a) »Original Income Stream« means the aggregate of the present values of the payments of principal and interest which would have become due to the Bank during the Calculation Period (as defined below) on the portion of the Loan which is subject to a Fixed Interest Rate if such prepayment, acceleration or cancellation had not occurred and if interest accrued on such portion of the Loan at the Relevant Market Interest Rate for such portion of the Loan.
(b) »Substitute Income Stream« means the sum of:
(1) the aggregate of the present values of any remaining payments of principal and interest which, after taking into account such prepayment, cancellation or acceleration, would become due to the Bank during the Calculation Period on the portion of the Loan which is subject to a Fixed Interest Rate if interest accrued on such portion of the Loan at the Relevant Market Interest Rate for such portion of the Loan; and
(2) as applicable:
(A) in the case of a prepayment pursuant to Section 3.07 of the Standard Terms and Conditions, the present value of the amount of the Loan to be prepaid, determined by discounting such amount from the date such prepayment becomes due to the Calculation Date (as defined below) at the Discount Rate (as defined below); and/or
(B) in the case of any other prepayment, the amount of the Loan which has been prepaid; and/or
(C) in the case of an acceleration, the present value of the amount of the Loan which has been accelerated, determined by discounting such amount from the date such acceleration becomes effective to the Calculation Date at the Discount Rate; and/or
(D) in the case of a cancellation, the present value of the amount of the Loan which has been cancelled, determined by discounting such amount from the Last Availability Date to the Calculation Date at the Discount Rate.
(c) For purposes of paragraphs (a) and (b)(1) above, the present value of each payment of principal and interest shall be determined by discounting the amount of such payment from its due date to the Calculation Date using the Discount Rate.
(d) »Calculation Date« means:
(1) in the case of a prepayment pursuant to Section 3.07 of the Standard Terms and Conditions, the date two Business Days prior to the date such prepayment becomes due or, at the Bankžs option, the date such prepayment becomes due;
(2) in the case of any other prepayment, the date such prepayment is made or such later date as the Bank may select in its discretion; and
(3) in the case of an acceleration or cancellation, the date two Business Days prior to the date such acceleration or cancellation becomes effective or, at the Bankžs option, the date such acceleration or cancellation becomes effective.
(e) »Calculation Period« means:
(1) in the case of a prepayment pursuant to Section 3.07 of the Standard Terms and Conditions, the period commencing on the date such prepayment becomes due and ending on the final Loan Repayment Date;
(2) in the case of any other prepayment, the period commencing on the date such prepayment is made, or such later date as the Bank may select in its discretion, and ending on the final Loan Repayment Date; and
(3) in the case of an acceleration or cancellation, the period commencing on the date such acceleration or cancellation becomes effective and ending on the final Loan Repayment Date.
(f) »Discount Rate« means the discount factor for the relevant maturity derived from the par swap curve for the Loan Currency which is available to the Bank in the interest rate swap and options market on the Calculation Date.«
(c) Section 3.10 of the Bankžs Standard Terms and Conditions dated February 1999 shall, for purposes of this Agreement, be modified to read as follows:
»Section 3.10. Unwinding Costs
(a) If, for any reason (including, without limitation, an acceleration pursuant to Section 7.06 of the Standard Terms and Condition), any portion of the Loan which is subject to a Variable Interest Rate becomes due and payable on a date other than the last day of an Interest Period, the Borrower shall pay to the Bank on demand the amount, if any, by which:
(1) the interest which would have accrued on such portion of the Loan from the date on which such portion of the Loan has become due and payable to the last day of the then current Interest Period at a rate equal to the Relevant Market Interest Rate for such portion of the Loan for such Interest Period;
exceeds:
(2) the interest which the Bank would be able to obtain if it were to place an amount equal to such portion of the Loan on deposit with a leading bank in the Euro-zone interbank market for the period commencing on the date on which such portion of the Loan has become due and payable and ending on the last day of the then current Interest Period.
(b) If, at any time:
(1) the Borrower gives a notice, pursuant to Section 3.07 of the Standard Terms and Conditions, of prepayment of any portion of the Loan which is subject to a Fixed Interest Rate or the Borrower otherwise prepays any such portion of the Loan;
(2) any portion of the Loan which is subject to a Fixed Interest Rate is accelerated pursuant to Section 7.06 of the Standard Terms and Conditions or otherwise becomes due prior to its stated maturity; or
(3) any portion of the Loan which is subject to a Fixed Interest Rate is cancelled pursuant to Section 3.08, 7.02 or 7.06 of the Standard Terms and Conditions or is otherwise cancelled;
the Borrower shall, in addition to any prepayment administrative fee, cancellation fee or other amounts payable in connection therewith, pay to the Bank on demand the amount of any Unwinding Costs; provided that, if the amount of such Unwinding Costs is negative, the Bank shall, on the next Interest Payment Date, credit to the Borrower, in the Loan Currency, the amount of such Unwinding Costs.
(c) If any overdue amount is paid on a date other than the last day of a Default Interest Period, the Borrower shall pay to the Bank on demand the amount, if any, by which:
(1) the interest which would have accrued on such overdue amount from the date of receipt of such overdue amount to the last day of the then current Default Interest Period at a rate equal to the rate specified in Section 3.09(a)(iii) of the Standard Terms and Conditions for such Default Interest Period;
exceeds:
(2) the interest which the Bank would be able to obtain if it were to place an amount equal to such overdue amount on deposit with a leading bank in the Euro-zone interbank market for the period commencing on the date of receipt of such overdue amount and ending on the last day of the then current Default Interest Period.
(d) A certificate of the Bank as to any amount payable under this Section 3.10 shall be final, conclusive and binding on the Borrower unless shown by the Borrower to the satisfaction of the Bank to contain manifest error.«
Section 1.02. Definitions
Wherever used in this Agreement (including the Preamble and Schedules), unless stated otherwise or the context otherwise requires, the terms defined in the Preamble have the respective meanings given to them therein, the terms defined in the Standard Terms and Conditions have the respective meanings given to them therein and the following terms have the following meanings:
»Borroweržs Authorised
Representative« means Dražen Ramljak, Director General of the Borrower.
»Eurocontrol« means the Eurocontrol International Convention relating to Co-operation for the Safety of Air Navigation of 13 December 1960, as amended in 1981 and 1997 and the Eurocontrol Agency created under the Convention.
»Fiscal Year« means the Borroweržs fiscal year commencing on 1 January of each year.
»Interest Conversion Date« means an Interest Payment Date selected by the Borrower as such in accordance with Section 2.02(h)(2)(B).
»Interest Fixing Date« means a Business Day selected by the Borrower as such in accordance with Section 2.02(h)(2)(B).
»PIU« means the project implementation unit referred to in Section 3.02.
»Reference Page« means the display of Euro-zone interbank offered rates for deposits in the Loan Currency designated as page 248 on Telerate (or such other page as may replace page 248 on Telerate for the purpose of displaying Euro-zone interbank offered rates for deposits in the Loan Currency).
»Statutes« means the Law on Establishing the Croatian Air Navigation Services, dated 5 February 1988, published in the Official Gazette No. 19, 1998 and the Statute of Hrvatska kontrola zračne plovidbe d.o.o. approved by the Croatian State Parliament on 11 June 1999.
»Strategic Business Plan« means the strategic business plan to be prepared by the Borrower according to the methodology developed by Eurocontrol which shall define the targeted Air Traffic Management service model for Croatia and detail the actions to be taken in order to meet this target against agreed key performance indicators, such as cost-efficiency indicators and the unit rate paid by users. The Strategic Business Plan shall also include feasibility indicators, both in terms of human resources available and implementation timetable.
Section 1.03. Interpretation
In this Agreement, a reference to a specified Article, Section or Schedule shall, except where stated otherwise in this Agreement, be construed as a reference to that specified Article or Section of, or Schedule to, this Agreement.
Article II - PRINCIPAL TERMS OF THE LOAN
Section 2.01. Amount and Currency
Nastavak dokumenta
Otvorite račun i odmah nastavite čitati od ovog mjesta.
Već imate račun? Prijavite se
Podaci o dokumentu, sažetak i poveznice dostupni su bez prijave.
Što uključuje pretplata