GUIDELINES SELECTION AND EMPLOYMENT
OF CONSULTANTS BY WORLD BANK BORROWERS
FOREWORD
i. These Guidelines: Selection and Employment of Consultants by World Bank Borrowers (January 1997) replace the 1981 Guidelines: Use of Consultants by World Bank Borrowers and the World Bank as Executing Agency. They take into account the following important developments, among others:
(a) diversification of Bank lending to new sectors and the need to address the specific issues that apply to the use of consultants in these new areas;
(b) Bankžs continuing policy to promote the development and use of consultants in Borrower countries;
(c) worldwide increased use of cost as a factor in the selection of consultants, in both the public and the private sectors;
(d) increased emphasis on transparency in the selection process;
(e) need for simplification of the selection and review process; and
(f) the Bankžs policy of entrusting the beneficiary with the selection of consultants funded by trust funds, with the Bank acting as executing agency only exceptionally.
ii. The basic principles underlying the procedures for selecting consultants financed under Bank operations remain the same: the overriding concern for quality of the services provided, with due attention to economy, efficiency, fair opportunity for all firms, and transparency of process.
I. INTRODUCTION
Purpose
1.1 The purpose of the Guidelines: Selection and Employment of Consultants by World Bank Borrowers (hereinafter referred to as »Guidelines«) is to define the procedures for selecting, contracting, and monitoring consultants required for projects that are financed in whole or in party by loans from the International Bank for Reconstruction and Development (IBRD), credits from the International Development Association (IDA), 1 or grants from the Bank or trust funds2 administered by the Bank and executed by the beneficiary.
1.2 The Loan Agreement governs the legal relationships between the Borrower and the Bank, and the Guidelines apply to the selection and employment of consultants for the project as provided in the Agreement. The rights and obligations of the Borrower3 and the Consultant are governed by the specific Request for Proposals (RFP) issued by the Borrower and by the contract signed by the Borrower with the Consultant, and not by these Guidelines or the Loan Agreement. No party other than the parties to the Loan Agreement shall derive any rights therefrom or have any claim to loan proceeds.
1.3 For the purpose of these Guidelines, the term consultants includes a wide variety of private and public entities, including consulting firms, engineering firms, construction managers, management firms, procurement agents, inspection agents, auditors, United Nations (UN) agencies and other multinational organizations, investment and merchant banks, universities, research institutions, government agencies, nongovernmental organizations (NGOs), and individuals.4 Bank Borrowers use these organizations as consultants to help in a wide range of activities - such as policy advice; institutional reforms; management; engineering services; construction supervision; financial services; procurement services; social and environmental studies; and identification, preparation, and implementation of projects - to complement Borrowersž capabilities in these areas.
General Considerations
1.4 The Borrower is responsible for preparing and implementing the project, and therefore for selecting the Consultant, and awarding and subsequently administering the contract. While the specific rules and procedures to be followed for employing consultants depend on the circumstances of the particular case, five main considerations guide the Bankžs policy on the selection process:
(a) the need for high-quality services,
(b) the need for economy and efficiency,
(c) the need to give qualified consultants from all eligible countries an opportunity to compete in providing the services financed by the Bank,
(d) the Bankžs interest in encouraging the development and use of national consultants in its developing member countries, and
(e) the importance of transparency in the selection process.
1.5 The Bank considers that, in the majority of cases, these considerations can best be addressed through competition among qualified short-listed firms in which the selection is based both on the quality of the proposal and on the cost of the services to be provided. (Quality-and Cost-Based Selection ŠQCBSĆ). Section II of these Guidelines describes the procedures for QCBS. However there are cases when QCBS is not the most appropriate method of selection. For complex or highly specialized assignments which invite innovations, selection based on the quality of the proposal alone (Quality-Based Selection (QBS)), as described in Section III, would be more appropriate. In addition, Section III describes other methods of selection and the circumstances in wicht they are appropriate.
1.6 The particular methods to be followed for the selection of consultants for any given project shall be selected by the Borrower in accordance with the criteria outlined in these Guidelines and agreed upon by the Bank and shall be specified in the Bankžs project documentation and the Loan Agreement for such project.
Applicability of Guidelines
1.7 The consulting services to which these Guidelines apply are of an intellectual and advisory nature. These Guidelines do not apply to other types of services in which the physical aspects of the activity predominate (for example, construction of works, manufacutre of goods, operation and maintenance of facilities or plant, surveys, exploratory drilling, aerial photography, and satellite imagery).5
1.8 The procedures outlined in these Guidelines apply to all contracts for consulting services financed in whole or in part from Bank loans or grants or trust funds6 implemented by the beneficiary. In procuring consulting services not financed from such sources, the Borrower may adopt other procedures. In such cases, the Bank shall satisfy itself that (a) the procudures to be used will result in the selection of consultants who have the necessary professional qualifications, (b) the selected Consultant will carry out the assignment in accordance with the agreed schedule, and (c) the scope of the services is consistent with the needs of the project.
Conflict of Interest
1.9 Bank policy requires that consultants provide professional, objective, and impartial advice and at all times hold the clientžs interests paramount, without any consideration for future work, and strictly avoid conflicts with other assignments or their own corporate interests. Consultants shall not be hired for any assignment that would be in conflict with their prior or current obligations to other clients, or that may place them in a position of not being able to carry out the assignment in the best interest of the Borrower. Withour limitation on the generality of this rule, consultants shall not be hired under the circumstances set forth below;
(a) A firm which has been engaged by the Borrower to provide goods or works for a project, and any of its affiliates, shall be disqualified from providing consulting services for same project. Conversely, a firm hired to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods or works or services related to the initial assignment (other than a continuation of the firmžs earlier consulting services as further described in paragraph 3.10) for the same project. This provision does not apply to the various firms (consultants, contractors, or suppliers) that together are performing the contractoržs obligations under a turnkey or design-and-build contract.
(b) consultants or any of their affiliates shall not be hired for any assignement which, by its nautre, may be in conflict with another assignment of the consultants. As an example, consultants hired to prepare engineering design for an infrastructure project shall not be engaged to prepare an independent environmental assessment for the same project, and consultants assisting a client in the privatization of public assets shall not purchase, nor advise purchasers of, such assets.
Eligibility
1.10 Only firms that are registered or incorporated in, and individuals and personnel who are nationals of, Bank member countries7 are eligible to compete for Bank-financed consulting services. However,
(a) Consultants from a member country may be excluded if (i) as a matter of law or official regulations, the Borroweržs country prohibits commercial relations with that country, provided that the Bank is satisfied that such exclusion does not preclude effective competition for the procurement of the consulting services required, or (ii) by an act of compliance with a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations, the Borroweržs country prohibits any payments to persons or entities in that country.
(b) Government-owned enterprises ih the Borroweržs country may participate only if they can establish that they (i) are legally and financially autonomous, and (ii) operate under commercial law. No dependent agency of the Borrower or Sub-Borrower of the procject or their employees shall be permitted to submit or participate in a proposal for the provison of consulting services under the project.
Advance Contracting and Retroactive Financing
1.11 In certain circumstances, such as to accelerate project implementation, the Borrower may, with the Bankžs agreement, wish to proceed with the selection of consultants before the related Bank loan is signed. This process is referred to as advance contracting. In such cases, the selection procedures shall be in accordance with these Guidelines, and the Bankžs normal review process shall be followed. A Borrower undertakes such advance contracting at its own risk, and any »no objection« issued by the Bank with regard to the procedures, documentation, or proposal for award does not commit the Bank to make a loan for the project in question. If the contract is signed, reimbursement by the Bank of any payments made by the Borrower under the contract prior to loan signing is referred to as retroactive financing and is only permitted within the limits specified in the Loan Agreement.
Associations Between Consultants
1.12 Consultants may associate with each other to complement their respective areas of expertise, or for other reasons. Such an association may be for the long term (independent of any particular assignment) or for a specific assignment. The »asociation« may take the form of a joint venture or of a subconsultancy. In case of a joint venture, all members of the joint venture shall sign the contract and shall be jointly and severally liable for the entire assignment. Once the short list is finalized, and Requests for Proposals (RFPs) are issued, any association in the form of joint venture or subconsultancy among short-listed firms shall be permissible only with the approval of the Borrower. Borrowers shall not require consultants to form associations with any specific firm or group of firms, but may encourage association with qualified national firms.
Bank Review, Assistance, and Monitoring
1.13 The Bank reviews the Borroweržs hiring of consultants to satisfy itself that the selection process is carried out in accordance with the provisions of the Loan Agreement. (The review procedures are described in Appendix 1).
1.14 Under special circumstances, the Bank may assist the Borrower in any or all the various steps of the selection process, such as the provision of short lists8 or long lists.9 In response to a written request from a Borrower, the Bank will furnish a short or long list of firms that it expects to be capalbe of undertaking the assignment. The provision of the list does not represent an endorsement of the consultants. The Borrower may delete or add other names as it wishes; however, the final short list shall be submitted to the Bank for its approval before issue of the RFP.
1.15 The Bank maintains an information system on consultants - Data on CONsultants (DACON). Registration in DACON is not mandatory to be considered for a Bank-financed assignment, nor is DACON a list of preapproved consultants. When firms register DACON, they provide information that may be useful to Borrowers and the Bank in the preparation of short lists and review of qualifications of firms proposed by Borrowers. The Bank does not verify of endorse the information provided. The Bank provides this information to member governments, UN agencies, and other public international bodies upon request, without any charge for the Borrowers and at a cost to others. The Bank may, with the consent of the firms, also provide nonconfidential information to other consultants interested in seeking associates or partners for assignments.
1.16 Borrowers are responsible for supervising the Consultantžs performance and ensuring that they carry out the assignment in accordance with the contract. Without assuming the responsibilities of the Borrower or the consultants, Bank staff shall monitor the work as necessary to satisfy themselves that it is being carried out according to appropriate standards, and is based on acceptable data. As appropriate, the Bank may take part in discussion between the Borrower and consultants and, if necessary, may help the Borrower in addressing issues related to the assignment. If a significant portion of project preparation work is being carried out in the consultantsžs home offices, Bank staff may, with the Borroweržs agreement, visit these offices to review the consultantžs work.
Reserved Consultant Services
1.17 If competitive process under these Guidelines would be the appropriate way of procuring certain consulting services, but the Borrower wishes to reserve these services for one or more specific firms, the Bank may accept such reserved selection only on condition that:
(a) the assignment is not eligible for financing out for the Bank loan; and
(b) it will not significantly affect the satisfactory project implementation in terms of cost, quality, and completion time.
Misprocurement
1.18 The Bank shall not finance expenditures for consulting services that have not been contracted in accordance with the agreed procedures in the Loan Agreement. In particular, the Bank will not finance a contract when the qualifications of the consultants or the terms and conditions of the contract are not satisfactory to the Bank. In such cases, the Bank will declare misprocurement, and it is the Bankžs policy to cancel that portion of the loan alocated to the services that have been misprocured. The Bank may, in addition, exercise other remedies under the Loan Agreement. Once the contract is awarded after obtaining a »no objection« from the Bank, the Bank may still declare misprocurement if it concludes that the »no objection« was issued on the basis of incomplete, inaccurate, or misleading information furnished by the Borrower.
References to the Bank
1.19 The Borrower shall use the following language10 when referring to the Bank in the RFP and contract documents:
»2Name of the Borrower3 has received 2or, žhas applied forž3 a loan from the International Bank for Reconstruction and Development (IBRD) in various currencies equivalent to US$…, toward the cost of 2name of project3, and intends to apply a portion of this loan to eligible payments under this Contract, Payments by IBRD will be made only at the request of 2name of Borrower or designate3 and upon approval by IBRD, and will be subject, in all respects, to the terms and conditions of the Loan Agreement. The Loan Agreement prohibits a withdrewal from the Loan Account for the purpose of any payment to persons or entities, or for any import of goods, if such payment or import, to the knowledge of the Bank, is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations. No party other than 2name of Borrower3 shall derive any rights from the Loan Agreement or have any claim to proceeds.«
Training or Transfer of Knowledge
1.20 If the assigment includes an important component for training or transfer of knowledge to Borrower staff or national consultants, the Terms of Reference (TOR) shall indicate the objectives, nature, scope, and goals of the training program, including details on trainers and trainees, skills to be transferred, time frame, and monitoring and evaluation arrangements. The cost for the training program shall be included in the consultantsž contract and in the budget for the assignment.
Language
1.21 The RFP and the proposal shall be prepared in either English, French, or Spanish at the choice of the Borrower. The text of the contract documents in that language shall govern.
1.22 The Borrower may, at its option and provided the national language is widely used, permit national consultants (excluding joint ventures between foreign and national firms), to submit their proposals and sign their contracts in the national language only, which shall then be the governing language for the contract. In such cases, the Bank shall be provided a translation of the firmžs proposal and the contract in the international language specified in the RFP for contracts subjects to prior review. Borrowers shall not ask firms to sign contracts both in a foreign and in the national language.
Evaluation of the Performance of Consultants
1.23 Consultants shall observe due diligence and prevailing standards in the performance of the assignment. The Bank shall evaluae the performance of consultants employed under Bank-financed contracts in a fair and confidential process. The performance ratings will be an input for future shortlisting. In the case of repeated poor performance, the firm will be notified and provided an opportunity to explain the reasons for it and the remedial action proposed. If poor performance persists, the Bank may exclude the firm from participation in Bank-financed assigments for a stated period.
1.24 Consultants shall be responsible for the accuracy and suitability of their work. Although Borrowers supervise and review the consultantžs work, no modifications shall be made in the final documents prepared by the consultant without mutual agreement. In the case of supervision of works, the Consultant may have more or less authority to supervise, from full responsibility as an independent engineer, to that of advisor to the clinet with little authority to make decisions.11
Fraud and Corruption
1.25 It is the Bankžs policy to require that Borrowers (including beneficiaries of Bank loans), as well as consultants under Bank-financed contracts, observe the highest standard of ethics during the selection and execution of such contracts. On pursuance of this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) »corrupt practice« means the offering, giving, receiving, or soliciting of any thing of value to influence the action of a public official in the selection process or in contract execution; and
(ii) »fraudulent practice« menas a misrepresentation of facts in order to influence a selection process or the execution of a contract to the detriment of the Borrower, and includes collusive practices among consultants (prior to or after submission of proposals) designed to establish prices at artificial, noncompetitive levels and to deprive the Borrower of the benefits of free and open compatition;
(b) will reject a proposal for award if it determines that the Consultant recommended for award has engaged in corrupt or fraudulent activities in competing for the contract in question;
(c) will cancel the portion of the loan allocated to the Consultantžs contract if it at any time determines that corrupt or fraudulent practices were engaged in by representatives for the Borrower or of a beneficiary of the loan during the selection process or the execution of that contract, without the Borrower having taken timely and appropriate action satisfactory to the Bank to remedy the situation;
(d) will declare a firm (or individual consultant) ineligible, either indefinitely or for a stated period of time, to be awarded a Bank-financed contract if it at any time determines that the firm (or the individual consultant) has engage in corrupt or fraudulent practices in competing for, or in executing, a Bank-financed contract; and
(e) will have the right to require that, in contracts financed by a Bank loan, a provision be included requiring consultants, suppliers, and contractors to permit the Bank to inspect their accounts and records relating to the performance of the contract and to have them audited by auditors appointed by the Bank.
II. QUALITY-AND COST-BASED SELECTION (QCBS)
The Selection Process
2.1. QCBS uses a competitive process among short-listed firms that takes into account the quality of the proposal and the cost of the services in the selection of the successful firm. Cost as a factor of selection shall be used judiciously. The relative weight to be given to the quality and cost shall be determined for each case depending on the nature of the assignment.
2.2. The selection process shall include the following steps:
(a) prepration of TOR;
(b) preparation of cost estimate and the budget:
(c) advertising
(d) preparation of the short list of consultants;
(e) preparation and issuance of the RFP;
(i) Letter of Invitation;
(ii) Information to Consultants;
(iii) proposed contract;
(f) receipt of proposals;
(g) evaluation of technical proposals; consideration of quality;
(h) evaluation of financial proposal;
(i) final evaluation of quality and cost; and
(j) negotiations and award of the contract to the selection firm.
Terms of Reference (TOR)
2.3. The Borrower shall be responsible for preparing the TOR for the assignment. TOR shall be prepared by a person(s) or a firm specialized in the area of the assignment. The scope of the services described in the TOR shall be compatible whith the available budget. TOR shall define clearly the objectives, goals, and scope of the assignment and provide background information (including a list of existing relevant studies and basic data) to facilitate the consultantsž preparation of their proposals. If transfer of knowledge or training is an objective, it should be specifically outlined along with details of number of staff to be trained, and so forth, to enable consultants to estimate the required resources. TOR shall list the services and surveys necessary to carry out the assignment and the expected outputs (for example, reports, data, maps, surveys). However, TOR should not be too detailed and inflexible, so that competing consultants may propose their own methodology and staffing. Firms shall be encouraged to comment on the TOR in their proposals. The Borroweržs and consultantsž respective responsibilities should be clearly defined in the TOR.
Cost Estimate (Budget)
2.4 Preparation of a well-thought-through cost estimate is essential if realistic budgetary resources are to be earmarked. The cost estimate shall be based on the Borroweržs assessment of the resources needed to carry out the assignment staff time, logistical support, and physical inputs (for example, vehicles, laboratory equipment). Costs shall be divided into two broad categories; (a) fee or remuneration (according to the type of contract used) and (b) reimbursables, and further divided into foreign and local costs. The cost of staff time shall be estimated on a realistic basis for foreign and national personnel.
Preparation and Issuance of Request for Proposals (RFP)
2.5 The RFP shall include (a) a Letter of Invitation, (b) Information to Consultants, (c) the TOR, and (d) the proposed contract Whenever possible, Borrowers shall use one of the standard RFPs issued by the Bank, and shall list all the documents included in the RFP.
Letter of Invitation (LOI)
2.6 The LOI shall state the intention of the Borrower to enter into a contract for the provision of consulting services, the source of funds, the details of the client and the date, time, and address for submission of proposals.
Information to Consultants (ITC)
2.7 The ITC shall contain all necessary iformation that would help consultants prepare responsive proposals, and shall bring as much transparency as possible to the selection procedure by providing information on the evaluation process and by indicating the evaluation criteria and factors and their respective weights and the minimum passing quality score. The ITC shall not indicate the budget (since cost is a selection criterion), but shall indicate the expected input of key professionals (staff time). Consultants, however, shall be free to prepare their own estimates of staff time necessary to carry out the assignment. The ITC shall specify the proposal validity period (normally 60-90 days). A detailed list of the information that should be included in the ITC is given in Appendix 2.
Contract
2.8 Section IV of these Guidelines briefly discusses the most common types of contracts. Borrowers shall use the appropriate Standard Form of Contract issued by the Bank with minimum changes, acceptable to the Bank, as necessary to address specific conutry and project issues. Any such changes shall be introduced only through Contract Data Sheets or through Special Conditions of Contract and not by introducing changes in the wording of the General Conditions of Contract included in the Bankžs Standard Form. These forms of contracts cover the majority of consulting services. When these forms are not appropriate (for example, for preshipment inspection, procurement services, training of students in universities, advertising activities in privatization, or twinning), Borrowers shall use other contract forms acceptable to the Bank.
Short list of Consultants
2.9 The Borrower is responsible for preparation of the short list. To obtain expressions of interest, the Borrower shall include a list of expected consulting assignments in the General Procurement Notice.12
In addition, it shall also advertise large-value contracts in a local newspaper and in Development Business (UNDB) and optionally in an international newspaper or a tehcnical magazine, seeking »expression of interest.« The Borrower may also contact embassies, professional organizations, or firms that it knows or that are registered in DACON.13 The information requested shal be the minimum required to make a judgment on the firmžs suitability and not be so complex as to discourage consultants from expressing interest. The Borrower shall give first consideration to those firms expressing interest which possess the relevant qualifications. Short lists shall comprise three to six firms with a wide geographic spread, with no more than two firms from any one country and at least one firm from a developing country, unless qualified firms from developing countries are not identifiable. For the purpose of establishing the short list, the nationality of a firm is that of the country in which it is registered or incorporated. The Bank may ask the Borrower to expand or reduce a short list; however, once the Bank has issued a »no objection« to a short list, the Borrower shall not add or delete names without the Bankžs concurrence.
2.10 The short list may comprise entirely national consultants (firms with majority national ownership and registered or incorporated in the country), if the assignment is small, a sufficient number of qualified firms (at least three) are available at competitive costs, and competition including foreign consultants is prima facie not justified.
Receipt of Proposals
2.11 The Borrower shall allow enough time for the consultants to prepare their proposals. The time allowed shall depend on the assignment, but normally shall not be less than four weeks or more than three months (for example, for assignments, requiring establishment of a sophisticated methodology, preparation of a multidisciplinary master plan). During this interval, the firms may request clarifications about the information provided in the RFP. The Borrower shall provide these clarifications in writing and copy them to all firms on the short list (who intend to submit proposals). If necessary, the Borrower shall extend the deadline for submission of proposals. The technical and financial proposals shall be submitted at the same time. No amendments to the technical or financial proposal shall be accepted after the deadline. To safeguard the integrity of the process, the technical and financial proposals shall be submitted in separate sealed envelopes. The technical envelopes shall be opened immediately by a committee of officials drawn from the relevant departments (technical, finance, legal, as appropriate), after the closing time for submission of proposals. The financial proposals shall remain sealed and shall be deposited with a reputable public auditor or independent authority until they are opened publicly. Any proposal recived after the closing time for submission of proposals shall be returned unopened.
Evaluation of Proposals: Consideration of Quality and Cost
2.12 The evaluation of the proposals shall be carried out in two stages: first the quality, and then the cost. Evaluators of technical proposals shall not have access to the financial proposals until the technical evaluation, including any Bank reviews and clearance, is concluded. Financial proposals shall be opened only thereafter. The evaluation shall be carried out in full conformity with the provisions of the RFP.
Evaluation of the Quality
2.13 The Borrower shall evaluate each technical proposal (using an evaluation committee of three or more specialists in the sector), taking into account several criteria: (a) the Consultantžs relevant experience for the assignment, (b) the quality of the methodology proposed, (c) the qualifications of the key staff proposed, (d) transfer of knowledge, and (e) the extent of participation by nationals among key staff in the performance of the assignment. Each criterion shall be marked on a scale of 1 to 100. Then the marks shall be weighted to become scores. The following weights are indicative, and may be adjusted for specific circumstances. The proposed weights shall be disclosed in the RFP.
Consultantžs specific 5 to 10 points
experience:
Methodology: 20 to 50 points
Key personnel: 30 to 60 points
Transfer of 0 to 10 points
knowledge:14
Local participation:15 0 to 10 points
Total: 100 points
2.14 The Borrower shall normally divide these criteria into subcriteria. For example, subcriteria under methodology might be innovationand level of detail. However, the number of subcriteria should be kept to the essential. The Bank recommends against the use of exceedingly detailed lists of subcriteria that may render the evaluation a mechanical exercise more than a professional assessment of the proposals.
2.15 The weight given to experience can be relatively modest, since this criterion has already been taken into account when short-listing the Consultant. More weight shall be given to the methodology in the case of more complex assignments (for example, multidisciplinary feasibility or management studies).
2.16 Evaluation of only the key personnel is recommended. Since key personnel ultimately determine the quality of performance, more weight shall be assigned to this criterion if the proposed assignment is complex. The Borrower shall review the qualifications and experience of proposed key personnel in their curricula vitae, which must be accurate, complete, and signed by an authorized official of the Consultant and the individual proposed. When the assignment depends critically on the performance of key staff, such as a Project Manager in a large team of specified individuals, it may be desirable to conduct interviews. The individuals shall be rated in the following three subcriteria, as relevant to the task:
(a) general qualifications: general education and training, length of experience, positions held time with the consulting firm, experience in developing countries, and so forth;
(b) adequacy for the assignment: education, training, and experience in the specific sector, field, subject, and so forth, relevant to the particular assignment; and
(c) experience in the region: knowledge of the local language, culture, administrative system, government organization, and so forth.
2.17 Borrowers shall evaluate each proposal on the basis of its responsiveness to the TOR. A proposal shall be considered unsuitable and shall be rejected at this stage if it does not respond to important aspects of the TOR or it fails to achieve a minimum technical score specified in the RFP.
2.18 At the end of the process, the Borrower shall prepare an evaluation report of the »quality« of the proposals. The report shall substantiate the results of the evaluation and describe the relative strengths and weaknesses of the proposals. All records relating to the evaluation, such as individual mark sheets, shall be retained until completion of the project.
Evaluation of Cost
2.19 After the evaluation of quality is completed, the Borrower shall notify those consultants whose proposals did not meet the minimum qualifying mark or were considered nonresponsive to the RFP and TOR, indicating that their financial proposals will be returned unopened after completing the selection process. The Borrower shall simultaneously notify the consultants that have secured the minimum qualifying mark, and indicate the date and time set for opening the financial proposals. The opening date shall not be sonner than two weeks after the notification date. The financial proposals shall be opened publicly in the presence of representatives of the consultants who choose to attend. The name of the consultant, the quality scores, and the proposed prices shall be read aloud and recorded when the financial proposals are opened, and a copy of this record shall be promptly sent to the Bank. The Borrower shall prepare the minutes of the public opening.
2.20 The Borrower shall then review the financial proposals. If there are any arithmetical errors, they shall be corrected. For the purpose of comparing proposals, the costs shall be converted to a single currency selected by the Borrower (local currency or fully convertible foreign currency) as stated in the RFP. The Borrower shall make this conversion by using the selling (exchange) rates for those currencies quoted by an official source (such as the Central Bank), or by a commercial bank, or by an internationally circulated newspaper for similar transactions. The RFP shall specify the source of the exchange rate to be used, and the date of that exchange rate, provided that the date shall not be earlier than four weeks prior to the deadline for submission of proposals, nor later than the original date of expiration of the period of validity of the proposal.
2.21 For the purpose of evaluation, »cost« shall exclude local taxes, but shall include other reimbursable expenses, such as travel, translation, report printing, or secretarial-expenses. The proposal with the lowest cost may be given a financial score of 100 and other proposals given financial scores that are inversely proportional to their prices. Alternatively, a directly proportional linear methodology may be used in allocating the marks for the cost. The methodology to be used shall be described in the RFP.
Combined Quality and Cost Evaluation
2.22 The total score shall be obtained by weighting the quality and cost scores and adding them. The weight for the »cost« shall be chosen, taking into account the complexity of the assignment and the relative importance of quality. Except for the type of services specified in Section III, cost shall not account for more than 30 points or less than 10 points out of a total score of 100. The proposed weightings for quality and cost shall be specified in the RFP. The firm obtaining the highest total score shall be invited for negotiations.
Negotiations and Award of Contract
2.23 Negotiations shall include discussions of the TOR, the methodology, staffing, Borroweržs inputs, and special conditions of the contract. These discussions shall not substantially alter the original TOR or the terms of the contract, lest the quality of the final product, its cost, and the relevance of the initial evaluation be affected. Major reductions in work inputs should not be made solely to meet the budget. The final TOR and the agreed methodology shall be incorporated in »Description of Services«, which shall form part of the contract.
2.24 The selected firm should not be allowed to substitute key staff, unless both parties agree that undue delay in the selection process makes such substitution unavoidable or that such changes are critical to meet the objectives of the assignment.16 If this is not the case and if it is established that key staff were offered in the proposal without confirming their availability, the firm may be disqualified and the process continued with the next ranked firm. The key staff proposed for substitution shall have qualifications equal to or better than the key staff initially proposed.
2.25 Financial negotiations shall include clarification of the consultantsž tax liability in the Borroweržs country (if any), and how this tax liability has been or would be reflected in the contract. Proposed unit rates for staff-months and reimbursables shall not be negotiated, since these have already been a factor of selection in the cost of the proposal, unless there are exceptional reasons.
2.26 If the negotiations fail to result in an acceptable contract, the Borrower shall terminate the negotiations and invite the next ranked firm for negotiations. The Borrower shall consult with the Bank prior to taking this step. The Consultant shall be informed of the reasons for termination of the negotiations. Once negotiations are commenced with the next ranked firm, the Borrower shall not reopen the earlier negotiations. After negotiations are successfully completed, the Borrower shall notify other firms on the short list that they were unsuccessful.
Rejection of All Proposals, and Reinvitation
2.27 The Borrower will be justified in rejecting all proposals only if all proposals are nonresponsive and unsuitable either because they present major deficiencies in complying with the TOR, or because they involve costs substantially higher than the original estimate. In the latter case, the feasibility of increasing the budget, or scaling down the scope of services in the negotiations with the winning firm should be investigated in consultation with the Bank. Before all the proposals are rejected and new proposals are invited, the Borrower shall notify the Bank, indicating the reasons for rejection of all proposals, and shall obtain the Bankžs »no objection« before proceeding with the rejection and the new process. The new process may include revising the RFP (including the short list) and the budget. These revisions shall be agreed upon with the Bank.
Confidentiality
2.28 Information relating to evaluation of proposals and recommundations concerning awards shall not be disclosed to the consultants who submitted the proposals or to other persons not officially concerned with the process, until the award of contract is notified to the successful firm.
III. OTHER METHODS OF SELECTION
General
3.1 In some circumstances, QCBS is not the most appropriate method for selecting consultants, and other methods are more appropriate. The particular selection methods and the type of services to which they apply are determined by agreement between the Bank and the Borrower and are specified in the Loan Agreement. This section describes other selection methods and the circumstances under which they are generally appropriate.
Quality-Based Selection (QBS)
3.2 QBS is appropriate for the following types assignments:
(a) complex or highly specialized assignments for which it is difficult to define precise TOR and the required input from the consultants, and for which the client expects the consultants to demonstrate innovation in their proposals (for example, country economic or sector studies, multisectoral feasibility studies, design of a hazardous waste remediation plant or of an urban master plan, financial sector reforms);
(b) assignments that have a high downstream impact and in which the objective is to have the best experts (for example, feasibility and structural engineering design of such major infrastructure as large dams, policy studies of national significance, management studies of large government agencies); and
(c) assignments that can be carried out in substantially different ways, such that proposals will not be comparable (for example, management advice, and sector and policy studies in which the value of the services depends on the quality of the analysis).
3.3. In QBS, the RFP shall request submission of a technical proposal only (without the financial proposal). The RFP shall not provide the estimated budget, but it may provide the estimated number of key staff time, specifying that this information is given as an indication only, and that consultants shall be free to propose their own estimates.
3.4 After evaluating the technical proposals using the same methodology, as in QCBS (paragraphs 2.13-2.18), the Borrower shall ask the Consultant with the highest ranked technical proposal to submit a detailed financial proposal. The Borrower and the Consultant shall then negotiate the financial proposal and the contract. All other aspects of the selection process shall be identical to those of QCBS. If, however, consultants are requested to provide financial proposals initially together with technical proposals, safeguards shall be built in as in QCBS (paragraph 2.11) to ensure that the price envelope of only the selected proposal is opened and the rest returned unopened, after the negotiations are successfully concluded.